Energy-saving system for reducing fuel viscosity of large heavy oil power station

By adopting solar heating and flue gas waste heat exchange system in large heavy oil power plants, the problems of high fuel viscosity and large water resources consumption of heavy oil power plants are solved, the thermal efficiency is improved and the inlet temperature of the desulfurization tower is reduced, and energy saving and water saving are achieved. Effect.

CN222012339UActive Publication Date: 2024-11-15HENNAN ELECTRIC POWER SURVEY & DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323643134.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-11-15
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

Large heavy oil power stations use high viscosity heavy oil, which leads to low efficiency of boilers, requires a large amount of steam heating and high smoke exhaust temperature, increases the inlet temperature of the desulfurization tower, and thus consumes a lot of water resources.

Method used

An energy-saving system was designed to heat the fuel using a primary solar heater and a flue gas waste heat exchanger, and ensure that the fuel reaches the appropriate viscosity through a secondary heater and a backup heater, reduce the flue gas temperature at the boiler outlet and reduce steam consumption. and desulfurization tower inlet temperature.

Benefits of technology

It has achieved reduced fuel viscosity, reduced steam consumption, improved thermal efficiency and water resource conservation, and is suitable for high-sulfur heavy oil power plants.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222012339U_ABST
    Figure CN222012339U_ABST
Patent Text Reader

Abstract

The utility model discloses an energy-saving system for reducing fuel oil viscosity of a large heavy oil power station. A fuel oil inlet pipeline is connected to the oil inlet end of a fuel oil boiler through a heater; a boiler outlet flue of the oil burning boiler is connected with a flue gas waste heat exchanger, the other end of the flue gas waste heat exchanger is connected with a desulfurization tower inlet flue, and the desulfurization tower inlet flue is connected with a wet desulfurization tower. And a water inlet of the flue gas waste heat exchanger is connected with a circulating water inlet pipeline. The flue gas waste heat exchanger is arranged on the boiler outlet flue, circulating water in the flue gas waste heat exchanger is heated by high-temperature flue gas from the outlet of the oil burning boiler, and low-temperature flue gas after heat exchange enters the desulfurizing tower. Two stages of heaters are arranged on the fuel oil pipeline, the first stage is a solar heater, and the second stage is a circulating water heater. The fuel oil pipeline is provided with a standby heat exchanger bypass. Therefore, fuel oil viscosity is reduced, steam consumption of a power station is reduced, total heat efficiency is improved, and meanwhile the temperature of an inlet of the desulfurizing tower is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a power station flue gas waste heat utilization system and a fuel oil heating system. Background Art

[0002] Large oil power plants mostly use heavy oil with high viscosity, so the fuel system of heavy oil power plants needs to consume a lot of steam to heat the heavy oil. Heavy oil power plants with high sulfur content have high exhaust gas temperature, low boiler efficiency, and need to be equipped with wet desulfurization facilities. High exhaust gas temperature will lead to higher inlet temperature of desulfurization tower, resulting in greater water consumption. Utility Model Content

[0003] The technical problem to be solved by the utility model is: the utility model provides an energy-saving system for reducing fuel viscosity in a large heavy oil power station, rationally utilizes solar energy and flue gas waste heat, and saves water resources while saving energy.

[0004] In order to achieve the above object, the utility model is realized by the following technical solutions:

[0005] An energy-saving system for reducing fuel viscosity in a large heavy oil power plant comprises a fuel oil boiler, wherein a fuel oil inlet pipeline is connected to the fuel oil inlet end of the fuel oil boiler through a heater; the boiler outlet flue of the fuel oil boiler is connected to a flue gas waste heat exchanger, the other end of the flue gas waste heat exchanger is connected to a desulfurization tower inlet flue, and the desulfurization tower inlet flue is connected to a wet desulfurization tower; the water inlet of the flue gas waste heat exchanger is connected to a circulating water inlet pipeline.

[0006] The heater arranged on the fuel oil inlet pipeline includes at least one primary solar heater, and the fuel oil is heated by the solar heater.

[0007] The output end of the first-level solar heater is connected to the oil outlet pipeline after the first-level heating of the fuel oil, and the other end of the oil outlet pipeline after the first-level heating of the fuel oil is connected to the second-level heater, and the output end of the second-level heater is connected to the oil outlet pipeline after the second-level heating of the fuel oil, and the oil outlet pipeline after the second-level heating of the fuel oil is connected to the fuel oil pipeline entering the boiler, and the fuel oil pipeline entering the boiler is connected to the oil inlet end of the fuel oil boiler.

[0008] The fuel oil inlet pipeline is also connected to a standby heater, which is connected to the boiler fuel oil pipeline through a fuel oil standby heating bypass, and then connected to the oil inlet end of the fuel oil boiler through the boiler fuel oil pipeline.

[0009] The circulating water inlet pipe is connected to the water inlet of the flue gas waste heat exchanger. The circulating water after heat exchange flows into the secondary heater through the circulating water outlet pipe. The secondary heater is connected to the circulating water cooling outlet pipe.

[0010] Compared with the prior art, the utility model has the following beneficial effects: the utility model sets a flue gas waste heat exchanger on the boiler outlet flue, and the high-temperature flue gas from the outlet of the oil-fired boiler heats the circulating water in the flue gas waste heat exchanger, and the low-temperature flue gas after heat exchange enters the desulfurization tower. A two-stage heater is set on the fuel pipeline, the first stage is a solar heater, and the second stage heater is a circulating water heater. A standby heat exchanger bypass is also set on the fuel pipeline. The fuel enters the boiler for combustion after being heated to the viscosity required by the burner. Therefore, the utility model can be applied to large-scale heavy oil power plant projects that burn high-sulfur heavy oil. It not only uses flue gas waste heat and solar energy to heat the fuel, reduces the fuel viscosity, reduces the steam consumption of the power station, and improves the total heat efficiency, but also reduces the inlet temperature of the desulfurization tower, reduces the consumption of process water in the desulfurization system, and saves water resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is the overall structure diagram of the utility model. DETAILED DESCRIPTION

[0012] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0013] In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0014] like Figure 1 As shown, an energy-saving system for reducing fuel viscosity in a large heavy oil power station includes a fuel boiler 1, a flue gas waste heat exchanger 2, a wet desulfurization tower 3, a secondary heater 4, a primary solar heater 5, a standby heater 6, a boiler outlet flue 101, a desulfurization tower inlet flue 102, a circulating water inlet pipe 103, a circulating water outlet pipe 104, a circulating water outlet pipe after cooling 105, a fuel standby heating bypass 106, a fuel inlet pipe 107, a fuel outlet pipe 108 after primary heating, a fuel outlet pipe 109 after secondary heating, and a boiler fuel pipe 110.

[0015] Specifically, an energy-saving system for reducing fuel viscosity in a large heavy oil power plant includes a fuel boiler 1, a fuel oil inlet pipeline 107 is connected to the oil inlet end of the fuel boiler 1 through a heater; the boiler outlet flue 101 of the fuel boiler 1 is connected to the flue gas waste heat exchanger 2, the other end of the flue gas waste heat exchanger 2 is connected to the desulfurization tower inlet flue 102, and the desulfurization tower inlet flue 102 is connected to the wet desulfurization tower 3; the water inlet of the flue gas waste heat exchanger 2 is connected to the circulating water inlet pipeline 103.

[0016] Furthermore, the heater provided on the fuel oil inlet pipeline 107 includes at least a first-stage solar heater 5, and the fuel oil is heated by the solar heater. Preferably, the output end of the first-stage solar heater 5 is connected to the fuel oil outlet pipeline 108 after the first-stage heating, and the other end of the fuel oil outlet pipeline 108 after the first-stage heating is connected to the second-stage heater 4, and the output end of the second-stage heater 4 is connected to the fuel oil outlet pipeline 109 after the second-stage heating, and the fuel oil outlet pipeline 109 after the second-stage heating is connected to the boiler fuel oil pipeline 110, and the boiler fuel oil pipeline 110 is connected to the fuel inlet end of the fuel oil boiler 1.

[0017] Furthermore, the fuel oil inlet pipeline 107 is also connected to a standby heater 6, which is connected to the boiler fuel oil inlet pipeline 110 through the fuel oil standby heating bypass 106, and then connected to the fuel inlet end of the fuel oil boiler 1 through the boiler fuel oil inlet pipeline 110. Here, the standby heater 6 is arranged in parallel with the primary solar heater 5.

[0018] For circulating water, the circulating water inlet pipe 103 is connected to the water inlet of the flue gas waste heat exchanger 2. In the flue gas waste heat exchanger 2, the circulating water exchanges heat with the flue gas from the fuel oil boiler 1. The circulating water after heat exchange flows into the secondary heater 4 through the circulating water outlet pipe 104. In the secondary heater 4, the circulating water is used to heat the fuel oil. Finally, the circulating water is discharged from the outlet pipe 105 after the circulating water is cooled.

[0019] The working principle and working process of the utility model are as follows:

[0020] A flue gas waste heat exchanger 2 is arranged on the boiler outlet flue 101 of the oil-fired boiler 1. The circulating water enters the flue gas waste heat exchanger 2 through the circulating water inlet pipe 103, and after absorbing the flue gas waste heat, enters the secondary heater 4 along the circulating water outlet pipe 104. The circulating water after the heat is absorbed by the oil is discharged through the outlet pipe 105 after being cooled by the circulating water. The cooled boiler flue gas enters the wet desulfurization tower 3 through the desulfurization tower inlet flue 102 for flue gas purification. The reduction of flue gas temperature will greatly reduce the consumption of desulfurization process water.

[0021] A primary solar heater 5 is provided on the fuel oil inlet pipeline 107. After being heated by the primary solar heater 5, the fuel oil enters the secondary heater 4 along the fuel oil outlet pipeline 108 after primary heating, and is discharged from the fuel oil outlet pipeline 109 after secondary heating after absorbing heat. Considering the working time of the primary solar heater 5 and the maintenance and shutdown of the secondary heater 4, a fuel oil standby heating bypass 106 and a standby heater 6 are provided. The fuel oil standby heating bypass 106 merges with the fuel oil outlet pipeline 109 after secondary heating and enters the boiler fuel oil pipeline 110. The fuel oil heating system utilizes flue gas waste heat and solar energy, reduces the energy consumption of the whole plant, and improves the thermal efficiency of the whole plant; at the same time, it reduces the flue gas temperature at the inlet of the desulfurization tower, reduces the process water consumption, and saves water resources.

[0022] Therefore, the utility model can be applied to large-scale heavy oil power plant projects that burn high-sulfur heavy oil. It not only utilizes flue gas waste heat and solar energy to heat the fuel, reduces fuel viscosity, reduces power plant steam consumption, and improves total thermal efficiency, but also reduces the desulfurization tower inlet temperature, reduces the consumption of process water in the desulfurization system, and saves water resources.

[0023] The above is only a preferred embodiment of the present invention. It should be pointed out that those skilled in the art can make several changes and improvements without departing from the overall concept of the present invention, and these should also be regarded as the protection scope of the present invention.

Claims

1. An energy-saving system for reducing fuel viscosity in a large heavy oil power plant, characterized by: It comprises an oil-fired boiler (1), wherein an oil-fired oil inlet pipeline (107) is connected to an oil inlet end of the oil-fired boiler (1) via a heater; a boiler outlet flue (101) of the oil-fired boiler (1) is connected to a flue gas waste heat exchanger (2), the other end of the flue gas waste heat exchanger (2) is connected to a desulfurization tower inlet flue (102), and the desulfurization tower inlet flue (102) is connected to a wet desulfurization tower (3); and a water inlet of the flue gas waste heat exchanger (2) is connected to a circulating water inlet pipeline (103).

2. The energy-saving system for reducing fuel viscosity in a large heavy oil power plant according to claim 1 is characterized by: The heater arranged on the fuel oil inlet pipeline (107) includes at least one first-stage solar heater (5), and the fuel oil is heated by the solar heater.

3. The energy-saving system for reducing fuel viscosity in a large heavy oil power plant according to claim 2 is characterized by: The output end of the first-stage solar heater (5) is connected to the oil outlet pipeline (108) after the first-stage heating of the fuel oil, the other end of the oil outlet pipeline (108) after the first-stage heating of the fuel oil is connected to the second-stage heater (4), the output end of the second-stage heater (4) is connected to the oil outlet pipeline (109) after the second-stage heating of the fuel oil, the oil outlet pipeline (109) after the second-stage heating of the fuel oil is connected to the boiler fuel oil pipeline (110), and the boiler fuel oil pipeline (110) is connected to the oil inlet end of the fuel oil boiler (1).

4. The energy-saving system for reducing fuel viscosity in a large heavy oil power plant according to claim 3 is characterized by: The fuel oil inlet pipeline (107) is also connected to a standby heater (6), and the standby heater (6) is connected to the boiler fuel oil inlet pipeline (110) through the fuel oil standby heating bypass (106), and then connected to the fuel inlet end of the fuel oil boiler (1) through the boiler fuel oil inlet pipeline (110).

5. The energy-saving system for reducing fuel viscosity in a large heavy oil power plant according to claim 1 is characterized by: The circulating water inlet pipe (103) is connected to the water inlet of the flue gas waste heat exchanger (2), and the circulating water after heat exchange flows into the secondary heater (4) through the circulating water outlet pipe (104). The secondary heater (4) is connected to the circulating water cooling outlet pipe (105).