Method and device for determining ideal power generation progress index of power plant

A technology for index determination and power plants, applied in data processing applications, instruments, forecasting, etc., can solve problems such as not considering the operation of the power grid, unreasonable power generation plans, etc., and achieve the effect of low difficulty, good load rate, and strong practicability

Active Publication Date: 2017-11-21
POWER DISPATCHING CONTROL CENT OF GUANGDONG POWER GRID CO LTD
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

This kind of power generation schedule index does not take into account the actual operation of the power grid, so the power generation plan formulated according to the power generation schedule index has defects such as irrationality

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method and device for determining ideal power generation progress index of power plant
  • Method and device for determining ideal power generation progress index of power plant
  • Method and device for determining ideal power generation progress index of power plant

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] The specific implementation of the method for determining the ideal power generation progress index of the power plant of the present invention will be described in detail below in conjunction with the accompanying drawings.

[0022] like figure 1 As shown, a method for determining an ideal power generation schedule index of a power plant includes steps:

[0023] S110. Obtain the monthly maximum output and maintenance information of each unit in the power plant, where the maintenance information includes maintenance capacity and maintenance days;

[0024] S120. Obtain the forecasted power generation load of the entire network for each month;

[0025] S130. Determine the power generation capacity of the power plant in each month according to the maximum output of each unit, the maintenance capacity, the number of maintenance days, and the number of days in each month;

[0026] S140. Obtain the annual power generation capacity of the power plant according to the monthly...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a method and device for determining an ideal power generation progress indicator of a power plant. The method comprises the steps that maximum output and maintenance information of all units of the power plant in every month are acquired; predicated power generation load of the whole network in every month is acquired; the power generation capacity of the power plant in every month is determined according to the maximum output, maintenance capacity and maintenance lasting days of each unit as well as the number of days in every month; the total amount of the power generation capacity of the power plant from January to the m month is determined according to the power generation capacity of the power plant in every month and the obtained annual power generation capacity of the power plant; a contract progress indicator of the m month power generation capacity of the power plant is determined according to the specific value of the total amount and the annual power generation capacity; the ideal power generation progress indicator of the power plant in the m month is determined according to the contract progress indicator, the predicated power generation load of every month, the number of days in the whole year and the number of days from January 1 of the year to the last day of the m month. According to the method and device for determining the ideal power generation progress indicator of the power plant, the actual operation condition of the grid is considered, and the provided ideal power generation progress indicator is more reasonable.

Description

technical field [0001] The invention relates to the technical field of power system dispatching operation, in particular to a method for determining an ideal power generation schedule index of a power plant and a device for determining an ideal power generation schedule index for a power plant. Background technique [0002] The monthly power generation plan is one of the central links in the operation of the electricity market. In the power trading work, it is usually necessary to decompose the annual power plan of the power plant into each month. When decomposing the power plan, the monthly load rate of the power plant should be balanced as much as possible to reduce the risk of dispatch operation. At the same time, the load rate of each power plant in the monthly plan should be as close as possible to maintain the fairness of dispatch. The completion progress of the annual plan is an important process control indicator, and a set of power generation progress indicators ne...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): G06Q10/04G06Q10/06G06Q50/06
CPCG06Q10/04G06Q50/06Y04S10/50
Inventor 刘思捷李嘉龙陈雨果王宁蔡秋娜林英明
Owner POWER DISPATCHING CONTROL CENT OF GUANGDONG POWER GRID CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products