A method and system for supporting formwork on the top of an overhead fertilizer trough

By setting up embedded connecting rods and hoisting devices on the fertilizer trough, and combining simulation optimization to design scaffolding and oblique struts, the deformation and slurry leakage problems caused by unstable settlement in the casting of the supporting mold on the fertilizer trough is solved, and the casting is achieved The stability and support of the process are improved.

CN117763692BActive Publication Date: 2024-11-05CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410038694.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-11
Publication Date
2024-11-05
Estimated Expiration
2044-01-11

AI Technical Summary

Technical Problem

When casting concrete components on the fertilizer trough, due to the unstable settlement of the fertilizer trough area, the scaffolding below the template has displacement and slurry leakage. Although the existing solution avoids the unstable settlement area, it leads to excessive span, and the middle area of ​​the template Lack of support leads to deformation and slurry leakage problems.

Method used

By setting up multiple embedded connecting rods, calculating unstable settlement zones and avoiding their positions, designing the parameters of scaffolding poles and oblique struts, installing a hoisting device to control the strong load point at the bottom of the template, and optimizing the scaffolding and The oblique strut parameters ensure the stability and support force of the template, and the deflection is monitored by sensors to adjust the hoisting device to control the deformation of the template.

Benefits of technology

It effectively avoids deformation and slurry leakage during the casting process, enhances the support strength in the middle of the template, solves the slurry leakage problem caused by large spans, and ensures the stability of the casting process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117763692B_ABST
    Figure CN117763692B_ABST
Patent Text Reader

Abstract

A method and system for supporting formwork on the top of an overhead fertilizer trough, relating to the technical field of supporting formwork on the top of a fertilizer trough, comprising: arranging a plurality of embedded connecting rods in a concrete structure of a building, calculating an unstable settlement area at the fertilizer trough, calculating the structure and distribution position of a scaffold according to the parameters of the template supported by the cast concrete member, wherein the position of the scaffold uprights avoids the unstable settlement area, calculating the parameters of the main diagonal bracing rods and the auxiliary diagonal bracing rods according to the parameters of the cast concrete member, calculating the strong load point at the bottom of the template according to the parameters of the cast concrete member and the supporting template, vertically arranging at least one jacking device below the strong load point of the template, calculating the size of a base plate installed at the bottom of the jacking device at different strong load points, installing the above structure according to the calculated parameters, and completing the template support at the top of the scaffold, etc., thereby solving the problem of leakage of slurry due to the large span in the casting process of the existing fertilizer trough support formwork.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of manure trough top formwork support, and in particular to an overhead manure trough top formwork support method and system. Background Art

[0002] When it is necessary to support the formwork and cast concrete components above the fertilizer trough, due to the unstable settlement of the fertilizer trough area, supporting the formwork directly on the fertilizer trough will cause the scaffolding below the formwork to be displaced, resulting in problems such as formwork cracking and leakage, and in severe cases, there is a risk of collapse. The existing solution is to support the scaffolding with a large span and avoid the unstable settlement area to avoid the displacement of the scaffolding below the formwork due to unstable settlement. Although the above method solves the displacement of the scaffolding due to unstable settlement, the span is too large because it avoids the unstable settlement area, so that the middle area of ​​the formwork has no support from the vertical poles. During the process of casting concrete components, the middle area of ​​the formwork will be deformed due to excessive deflection, resulting in leakage. Summary of the Invention

[0003] The embodiment of the present invention provides a method and system for supporting formwork on the top of an overhead fertilizer trough, which solves the problem that the existing fertilizer trough top formwork casting method is prone to slurry leakage due to the large span.

[0004] A method for supporting formwork on the top of an overhead fertilizer trough comprises the following steps:

[0005] A plurality of pre-buried connecting rods are provided in the concrete structure of the building;

[0006] Calculate the unstable settlement area at the fertilizer trough and mark the unstable settlement area;

[0007] Calculate the structure and distribution of the scaffolding based on the parameters of the formwork supported by the poured concrete components, with the scaffolding uprights positioned to avoid unstable settlement areas;

[0008] Calculate the parameters of the main diagonal braces and auxiliary diagonal braces based on the parameters of the poured concrete components;

[0009] Calculate the strong load point at the bottom of the formwork based on the parameters of the concrete components to be poured and the formwork support;

[0010] At least one jacking device is vertically arranged below the strong load point of the formwork;

[0011] Calculate the size of the base plate installed at the bottom of the jacking device at different strong load points;

[0012] After installing the above structure according to the calculated parameters, the formwork is supported on the top of the scaffolding.

[0013] Furthermore, the jacking device includes a hydraulic rod vertically installed on the base plate and a push rod vertically connected to the output shaft of the hydraulic rod, and the other end of the push rod is connected to the strong load point at the bottom of the template.

[0014] Furthermore, the steps for calculating the scaffolding distribution position are as follows:

[0015] Construct the BIM level 1 model of the scaffolding;

[0016] Construct a simulation environment to simulate the process of formwork casting concrete components;

[0017] After optimizing the BIM primary model of the scaffolding, a BIM secondary model of the scaffolding that meets the usage requirements is obtained;

[0018] Obtain the structure of the scaffolding and the distribution position of the uprights in the non-settlement area.

[0019] Furthermore, the parameters of the main diagonal braces and the auxiliary diagonal braces include slope, position, size and quantity.

[0020] Furthermore, the calculation process of the parameters of the main diagonal brace and the auxiliary diagonal brace is as follows:

[0021] Import scaffolding BIM secondary model;

[0022] Construct a simulation environment to simulate the process of formwork casting concrete components;

[0023] Calculate the main support point and auxiliary support point;

[0024] Continue the simulation and adjust the parameters of the main diagonal braces and auxiliary diagonal braces until the requirements are met to obtain the scaffolding BIM level 3 model;

[0025] Export the parameters of the main and secondary diagonal braces.

[0026] Furthermore, the steps for calculating the strong load point are as follows:

[0027] Import the BIM level 3 model of the scaffolding;

[0028] Construct a simulation environment to simulate the process of formwork casting concrete components;

[0029] The simulation process is monitored to calculate the strong load points at the bottom of the formwork during construction.

[0030] Furthermore, the size of the base plate is determined according to the size of the load and the bearing capacity of the unstable settlement zone, and is directly proportional to the size of the load.

[0031] In a second aspect, an embodiment of the present invention provides an overhead fertilizer trough top formwork system, comprising:

[0032] The first calculation module is adapted to calculate the unstable settlement area at the fertilizer tank and mark the unstable settlement area;

[0033] The second calculation module is suitable for calculating the structure of the scaffold and the parameters of the main diagonal braces and the auxiliary diagonal braces;

[0034] The third calculation module is suitable for calculating the strong load point at the bottom of the template;

[0035] The fourth calculation module is suitable for monitoring the deflection at the strong load point and controlling the deflection at the strong load point through the jacking device template.

[0036] Furthermore, it also includes a server, and the first to third calculation modules are installed on the server. The deflection at the strong load point is collected and calculated by the sensor installed at the strong load point of the template to obtain the adjustment amount of the jacking device, and at the same time the jacking device is controlled to control the deflection at the strong load point of the template.

[0037] The beneficial effects of the above technical solutions provided by the embodiments of the present invention include at least:

[0038] The present invention simulates the calculated scaffolding structure to obtain the parameters of the main diagonal bracing rods and the auxiliary diagonal bracing rods used to enhance the supporting strength of the middle part of the formwork. At the same time, the strong load point at the bottom of the formwork is calculated and the corresponding jacking device is set to control the deflection of the strong load point, thereby supporting the strong load point of the formwork and avoiding deformation of the formwork during the pouring process, thus solving the problem of slurry leakage that is prone to occur during the pouring process using the existing fertilizer trough upper formwork.

[0039] Other features and advantages of the present invention will be described in the following description, and in part will become apparent from the description, or will be understood by practicing the present invention. The purposes and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description, claims, and drawings.

[0040] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0042] Figure 1 A schematic diagram of the process of the method for supporting formwork on the top of an overhead fertilizer trough disclosed in an embodiment of the present invention;

[0043] Figure 2 This is a schematic diagram of the top formwork structure of an overhead fertilizer trough disclosed in an embodiment of the present invention;

[0044] Figure 3 This is a schematic structural diagram of the formwork system for the top of an overhead fertilizer trough disclosed in an embodiment of the present invention.

[0045] Reference numerals:

[0046] 1. Scaffolding; 101. Vertical pole; 2. Main diagonal brace; 3. Auxiliary diagonal brace; 4. Base plate; 5. Hydraulic rod; 6. Top rod; 7. Non-settlement area; 8. Unstable settlement area; 9. Building; 10. Formwork; 11. Embedded connecting rod; 12. Server; 13. Sensor; 14. First computing module; 15. Second computing module; 16. Third computing module; 17. Fourth computing module; 18. Client; 19. Controller; 20. Data transceiver. DETAILED DESCRIPTION

[0047] Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. Rather, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art.

[0048] like Figures 1-2 As shown, an embodiment of the present invention provides a method for supporting the top of an overhead fertilizer trough, comprising the following steps:

[0049] S1, calculate the unstable settlement area at the fertilizer tank and mark the unstable settlement area 8;

[0050] In one embodiment, a comprehensive analysis is performed using geophysical methods and soil mechanics methods such as geological drilling, in-situ tests, and indoor geotechnical tests to determine parameters such as the engineering properties, soil layer structure, and physical and mechanical indicators of the soil at the fertilizer trough. Calculations are then combined to determine and predict unstable areas, and the unstable areas are marked after being identified.

[0051] By identifying the unstable settlement area at the fertilizer tank, the unstable settlement area 8 can be avoided during the erection of the scaffolding 1, thereby preventing the formwork 10 from cracking and slurry leakage due to settlement during the pouring process.

[0052] S2, calculating the structure and distribution position of the scaffolding 1 according to the parameters of the formwork 10 supported by the poured concrete component, wherein the position of the scaffolding 1 uprights 101 avoids the unstable settlement area 8;

[0053] Specifically, the parameters of the concrete component include the shape and mass distribution data of the concrete component; the parameters of the support template 10 include the support range, support structure, size and requirements for the scaffolding 1; based on the above parameters, the steps for calculating the distribution position of the scaffolding 1 are as follows:

[0054] Construct the BIM level 1 model of scaffolding 1;

[0055] Construct a simulation environment to simulate the process of formwork casting concrete components;

[0056] After optimizing the BIM primary model of scaffolding 1, a BIM secondary model of scaffolding 1 that meets the usage requirements is obtained;

[0057] The structure of the scaffold 1 and the distribution position of the uprights 101 in the non-settlement area 7 are obtained according to the scaffold 1bim secondary model.

[0058] S3, installing a plurality of pre-buried connecting rods 11 in the concrete structure of the building 9;

[0059] Specifically, the embedded connecting rod 11 is connected with the steel bars in the building 9 for casting, and the contact position between the secondary model of the scaffolding 1bim and the wall of the building 9 is determined.

[0060] It should be noted that one side of the scaffolding 1 is supported in the non-settlement area 7, and the other side is rigidly connected to the embedded connecting rod 11. The scaffolding 1 is supported by the building 9, which not only avoids settlement but also increases the supporting force, thereby improving the stability of the scaffolding 1 during use.

[0061] S4, calculating the parameters of the main diagonal brace 2 and the auxiliary diagonal brace 3 according to the parameters of the cast concrete component, the parameters of the main diagonal brace 2 and the auxiliary diagonal brace 3 including slope, position, size and quantity;

[0062] Specifically, the calculation process of the parameters of the main diagonal brace 2 and the auxiliary diagonal brace 3 is as follows:

[0063] Import scaffolding 1bim secondary model;

[0064] Construct a simulation environment to simulate the process of formwork casting concrete components;

[0065] Calculate the main support point and auxiliary support point;

[0066] Continue the simulation and adjust the parameters of the main diagonal brace 2 and the auxiliary diagonal brace 3 until the requirements are met, and obtain the scaffolding 1 BIM three-level model;

[0067] Derive the parameters of the main diagonal brace 2 and the auxiliary diagonal brace 3.

[0068] S5, calculating the strong load point at the bottom of the formwork 10 based on the parameters of the poured concrete components and the supporting formwork 10;

[0069] Specifically, the steps for calculating the strong load point are as follows:

[0070] Import the BIM level 3 model of scaffolding 1;

[0071] Construct a simulation environment to simulate the process of formwork casting concrete components;

[0072] The simulation process is monitored to calculate the strong load point at the bottom of the template 10 during the construction process.

[0073] S6, vertically arrange at least one jacking device below the strong load point of the template 10;

[0074] It should be noted that the position and number of the jacking devices correspond one-to-one to the position and number of the strong load points. The jacking device includes a hydraulic rod 5 vertically installed on the base plate 4 and a push rod 6 vertically connected to the output shaft of the hydraulic rod 5. The other end of the push rod 6 is connected to the strong load point at the bottom of the template 10.

[0075] In a preferred embodiment, a sensor 13 is installed at the strong load point of the template 10 to collect the deflection at the strong load point. The sensor 13 collects the data through the controller 19 and then communicates with the server 12 through the data transceiver 20. The collected data is uploaded to the server 12. The server 12 analyzes the deflection and obtains the adjustment amount of the hydraulic rod 5 of different jacking devices. The amount is sent to the controller 19 through the data transceiver 20. The controller 19 controls the hydraulic rod 5 to change the length of the jacking device so that it provides a reaction force to control the deflection at the strong load point of the template 10, thereby further reducing leakage.

[0076] In the above embodiment, the sensor 13 is a deflection sensor 13, the signal output end of the sensor 13 is communicatively connected to the signal input end of the controller 19, the signal input / output end of the controller 19 is communicatively connected to the signal input / output end of the data transceiver 20 respectively, and the signal input / output end of the data transceiver 20 is communicatively connected to the signal input / output end of the server 12.

[0077] The above-mentioned method can also be manually controlled to adjust the length of the hydraulic rod 5 so that it provides a reaction force to control the deflection at the strong load point of the template 10, thereby further reducing leakage.

[0078] S7, calculating the size of the base plate 4 installed at the bottom of the jacking device at different strong load points. The size of the base plate 4 is determined according to the size of the load and the bearing capacity of the unstable settlement zone 8, and is directly proportional to the size of the load;

[0079] The size of the base plate 4 S (㎡) = load N (KN) / the bearing capacity of the unstable settlement area 8 F (PA)

[0080] S8, after installing the above structure according to the calculated parameters, the template 10 is set up on the top of the scaffold 1.

[0081] The embodiment of the present invention also discloses a formwork system for the top of an overhead fertilizer trough, such as Figures 1 to 3 , including the first to third calculation modules 16 installed on the server, a sensor 13 is installed at the strong load point of the template 10 to collect the deflection at the strong load point, the sensor 13 collects the data through the controller 19 and then communicates with the server 12 through the data transceiver 20, and uploads the collected data to the server 12. The server 12 analyzes the deflection and obtains the adjustment amount of the hydraulic rod 5 of different jacking devices, and sends it to the controller 19 through the data transceiver 20. The controller 19 controls the hydraulic rod 5 to change the length of the jacking device so that it provides a reaction force to control the deflection at the strong load point of the template 10, further reducing slurry leakage:

[0082] Specifically, the first calculation module 14 is adapted to calculate the unstable settlement area 8 at the fertilizer tank and mark the unstable settlement area 8;

[0083] Specifically, the second calculation module 15 is adapted to calculate the structure of the scaffold 1 and the parameters of the main diagonal braces 2 and the auxiliary diagonal braces 3;

[0084] Specifically, the third calculation module 16 is adapted to calculate the strong load point at the bottom of the template 10;

[0085] Specifically, the fourth calculation module 17 is suitable for monitoring the deflection at the strong load point and controlling the deflection at the strong load point through the jacking device template 10.

[0086] The present invention obtains the parameters of the main diagonal brace 2 and the auxiliary diagonal brace 3 for enhancing the supporting strength of the middle part of the formwork 10 by simulating the calculated scaffolding 1 structure. At the same time, the strong load point at the bottom of the formwork 10 is calculated and a corresponding jacking device is set to control the deflection of the strong load point, thereby supporting the strong load point of the formwork 10 and avoiding deformation of the formwork 10 during the pouring process, thereby solving the problem of leakage during the pouring process using the existing fertilizer trough upper formwork.

[0087] It should be understood that the specific order or hierarchy of steps in the disclosed processes is an example of an exemplary method. Based on design preferences, it should be understood that the specific order or hierarchy of steps in the process can be rearranged without departing from the scope of the present disclosure. The accompanying method claims present elements of the various steps in an exemplary order and are not intended to be limited to a specific order or hierarchy.

[0088] In the foregoing detailed description, various features are grouped together in a single embodiment to simplify the disclosure. This method of disclosure should not be interpreted as reflecting an intention that embodiments of the claimed subject matter require more features than are expressly recited in each claim. On the contrary, as reflected in the appended claims, the invention comprises less than all the features of any individual disclosed embodiment. The appended claims are therefore hereby expressly incorporated into the detailed description, with each claim standing on its own as a separate preferred embodiment of the invention.

[0089] Those skilled in the art will also appreciate that the various illustrative logic blocks, modules, circuits, and algorithmic steps described in conjunction with the embodiments herein may be implemented as electronic hardware, computer software, or a combination thereof. In order to clearly illustrate the interchangeability between hardware and software, the various illustrative components, blocks, modules, circuits, and steps described above are generally described around their functions. Whether such functions are implemented as hardware or software depends on the specific application and the design constraints imposed on the entire system. A skilled person may implement the described functions in an adaptable manner for each specific application, but such implementation decisions should not be interpreted as departing from the scope of protection of this disclosure.

[0090] The steps of the methods or algorithms described in conjunction with the embodiments herein may be directly embodied as hardware, software modules executed by a processor, or a combination thereof. The software module may be located in a RAM memory, flash memory, ROM memory, EPROM memory, EEPROM memory, register, hard disk, removable disk, CD-ROM, or any other form of storage medium well known in the art. An exemplary storage medium is connected to the processor so that the processor can read information from the storage medium and write information to the storage medium. Of course, the storage medium may also be an integral part of the processor. The processor and storage medium may be located in an ASIC. The ASIC may be located in a user terminal. Of course, the processor and storage medium may also be present in a user terminal as discrete components.

[0091] For software implementation, the techniques described in this application can be implemented using modules (e.g., procedures, functions, etc.) that perform the functions of the application. These software codes can be stored in a memory unit and executed by a processor. The memory unit can be implemented within the processor or external to the processor. In the latter case, it is communicatively coupled to the processor via various means, which are well known in the art.

[0092] The foregoing description includes examples of one or more embodiments. Of course, it is not possible to describe all possible combinations of components or methods for the purposes of describing the above embodiments, but one of ordinary skill in the art will recognize that the various embodiments may be further combined and arranged. Therefore, the embodiments described herein are intended to encompass all such changes, modifications and variations that fall within the scope of the appended claims. Furthermore, to the extent the term "comprising" is used in the specification or claims, the term is intended to be encompassed in a manner similar to the term "including," as explained in terms of "including," used as a transitional word in the claims. Furthermore, any use of the term "or" in the specification of the claims is intended to mean a "non-exclusive or."

Claims

1. A method for supporting the top of an overhead fertilizer tank, characterized in that: The following steps are involved: Calculate the unstable settlement area at the fertilizer tank and mark the unstable settlement area; According to the parameters of the formwork supported by the poured concrete components, the structure and distribution position of the scaffolding are calculated, wherein the position of the scaffolding poles avoids the unstable settlement area; A plurality of pre-buried connecting rods are provided in the concrete structure of the building; Calculate the parameters of the main diagonal braces and auxiliary diagonal braces according to the parameters of the poured concrete components; Calculate the strong load point at the bottom of the formwork according to the parameters of the concrete components to be poured and constructed and the supporting formwork; At least one jacking device is vertically arranged below the strong load point of the formwork; Calculate the size of the base plate installed at the bottom of the jacking device at different strong load points; After installing the above structure according to the calculated parameters, the formwork is supported on the top of the scaffolding.

2. The method for supporting the top of an overhead fertilizer tank as claimed in claim 1, characterized in that: The jacking device comprises a hydraulic rod vertically mounted on the base plate and a push rod vertically connected to the output shaft of the hydraulic rod, and the other end of the push rod is connected to the strong load point at the bottom of the template.

3. The method for supporting the top of an overhead fertilizer tank according to claim 1, characterized in that: The steps to calculate the scaffolding distribution location are as follows: Construct the BIM level 1 model of the scaffolding; Construct a simulation environment to simulate the process of formwork casting concrete components; After optimizing the BIM primary model of the scaffolding, a BIM secondary model of the scaffolding that meets the usage requirements is obtained; The structure of the scaffolding and the distribution position of the uprights in the non-settlement area are obtained.

4. The method for supporting the top of an overhead fertilizer tank according to claim 1, characterized in that: The parameters of the main diagonal braces and the auxiliary diagonal braces include slope, position, size and quantity.

5. The method for supporting the top of an overhead fertilizer tank as claimed in claim 3, characterized in that: The calculation process of the parameters of the main diagonal brace and the auxiliary diagonal brace is as follows: Import scaffolding BIM secondary model; Construct a simulation environment to simulate the process of formwork casting concrete components; The main support point and the auxiliary support point are calculated; Continue the simulation, adjust the parameters of the main diagonal braces and auxiliary diagonal braces until the requirements are met, and obtain the scaffolding BIM level 3 model; Export the parameters of the main and secondary diagonal braces.

6. The method for supporting the top of an overhead fertilizer tank as claimed in claim 5, characterized in that: The steps to calculate the strong load point are as follows: Import the BIM level 3 model of the scaffolding; Construct a simulation environment to simulate the process of formwork casting concrete components; The simulation process is monitored to calculate the strong load points at the bottom of the formwork during construction.

7. The method for supporting formwork on the top of an overhead fertilizer tank as claimed in claim 1, characterized in that: The size of the base plate is determined according to the size of the load and the bearing capacity of the unstable settlement zone, and is directly proportional to the size of the load.

8. An overhead fertilizer tank top formwork system, using the overhead fertilizer tank top formwork method according to any one of claims 1 to 7, characterized in that: include: A first calculation module is adapted to calculate the unstable settlement area at the fertilizer tank and mark the unstable settlement area; The second calculation module is suitable for calculating the structure of the scaffold and the parameters of the main diagonal braces and the auxiliary diagonal braces; The third calculation module is suitable for calculating the strong load point at the bottom of the template; The fourth calculation module is suitable for monitoring the deflection at the strong load point and controlling the deflection at the strong load point through the jacking device template.

9. The overhead fertilizer tank top formwork system according to claim 8, characterized in that: It also includes a server, and the first to third calculation modules are installed on the server. The deflection at the strong load point is collected and calculated by the sensor installed at the strong load point of the template, so as to obtain the adjustment amount of the jacking device, and at the same time, the jacking device is controlled so that it controls the deflection at the strong load point of the template.