Shield tunnel construction ground settlement control method

A ground subsidence and tunnel construction technology, which is applied in tunnels, tunnel linings, underground chambers, etc., can solve problems such as differences in construction techniques and technologies, construction difficulties, etc., and achieve the effects of ensuring project safety, reducing costs, and reducing disturbances

Inactive Publication Date: 2012-07-25
TIANJIN URBAN CONSTR TUNNEL
View PDF4 Cites 10 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

With the in-depth research of shield tunneling method and the increase of engineering applications, the construction technology of shield tunneling method has been developed and improved. In recent years, shield tunneling technology has made significant progress. There are also differences in the mastery of the construction techniques and technologies of different methods. Although the national and some local standards can control the surface settlement within +10~-30mm, tunnels can be excavated safely at a distance of less than 1m from existing buildings and structures. The deformation of buildings and structures can be controlled below 2-5mm and other surrounding environmental protection issues have been uniformly stipulated, but some problems are still prone to occur in the application, which is always one of the construction problems

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0009] Take the construction technical measures of shield tunneling through Dieqiao Apartment Building 1 as an example:

[0010] A. Technical clarification before resuming excavation

[0011] Before resuming the excavation, the chief engineer of the project will conduct a systematic and all-round technical disclosure to the construction team for various problems and technical control measures that may be encountered in the foundation of the shield tunneling pile foundation, so that every step and every parameter of the construction is accurate. To ensure that the construction of this section can be carried out safely and smoothly.

[0012] B. Determine the crossing construction parameters

[0013] a. The frontal balance pressure P is based on theoretical calculations and the accumulated and summarized soil conditions during actual construction. Considering the external load of the building, we will adjust the frontal balance pressure P according to the ground monitoring repor...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a shield tunnel construction ground settlement control method, which includes the stages of construction preparation, trial excavation, formal excavation and shield tail leakage. The method particularly includes: using an initially tunneling section of front 100m as a trial tunneling section, dividing the trial put section of 100m into three sections, establishing control measures for tunneling for the third section, control for ground settlement and tunnel axes, lining installation quality and the like, and basically mastering construction parameters including tunneling speed, the volume of excavated earth of each turn, the water injection rate of each turn, shield deviation rectifying amplitude, synchronous grouting amount and slurry quality; and determining a shield tunneling axis according to the construction parameters measured at the construction preparation stage, and performing formal excavation according to the shield tunneling axis. By the aid of the construction technique, a reinforcing and moving range can be narrowed to the minimum extent, shield construction is performed at a uniform speed in a balanced manner, disturbance of shield tunneling change to soil is decreased, the overall construction cost of a project is reduced, and the requirement of ground settlement control is met.

Description

technical field [0001] The invention relates to the technical field of tunnel construction, in particular to a method for controlling ground subsidence during tunnel construction. Background technique [0002] After the 1990s, many cities in our country began to launch subway projects, and began to introduce and apply international advanced shield construction technology and equipment on a large scale. The subway projects were rapidly constructed in some cities, and the ground subsidence technology covered by them developed accordingly. my country's application of the shield method to build tunnels began in Shanghai in the 1950s and 1960s. With the in-depth research of shield tunneling method and the increase of engineering applications, the construction technology of shield tunneling method has been developed and improved. In recent years, shield tunneling technology has made significant progress. There are also differences in the mastery of the construction techniques an...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E21D9/06E21D11/00E21D11/38
Inventor 季岩涛
Owner TIANJIN URBAN CONSTR TUNNEL
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products