Sandbeach-staying-waiting construction method of cutter suction dredger

A technology of cutter suction dredger and construction method, which is applied in ship construction, ship parts, earth mover/shovel, etc., can solve the problems of frequent assembly and disassembly, low effective utilization rate of ships, long time consumption, etc., and achieves economical efficiency. Significant benefits, increase effective construction time, and improve the effect of construction time utilization

Active Publication Date: 2016-05-25
SDC WATERWAY CONSTR
View PDF5 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Due to the small range of water depth changes in muddy tidal flats, the range of low-tide exposed beaches is relatively large (up to 5 kilometers), and large cutter suction dredgers are non-self-propelled dredgers, and access to the soil borrowing area must rely on auxiliary ships ( Anchor boats, tugboats), and the distance of entry and exit is long and time-consuming. According to the normal draft requirements of the ship, the tide level that can be constructed in one day is only 1-2 hours. It g...

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Sandbeach-staying-waiting construction method of cutter suction dredger

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0014] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments.

[0015] The construction method of the cutter suction dredger provided by the present embodiment mainly includes the following steps:

[0016] 1. Select a ship nest area without hard foreign objects, and make the cutter suction dredger sail to the soil borrowing area when the tide level meets the draft conditions with the cooperation of auxiliary ships, and start to excavate the ship after quickly completing the assembly of the mud discharge pipeline on the water The nest, the size of the boat nest must be larger than the size of the cutter suction dredger, and the thickness of the excavated mud layer is 6 to 6.5 meters;

[0017] Step 2. Monitor the change of tidal water level in real time through the tide level remote indicator. After the water depth cannot meet the draft requirements, the cutter suction dredger will directly run aground in th...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a sandbeach-staying-waiting construction method of a cutter suction dredger. The sandbeach-staying-waiting construction method is characterized by including the steps that a dredger pit area without hard foreign matter is selected, and the cutter suction dredger is sailed to a soil taking area to excavate a dredger pit when the sea level meets the drafting condition; when the water depth can not meet the drafting condition, the cutter suction dredger stays on a sandbeach and is stranded to wait till the sea level rises again; after the water depth meets the requirement and the cutter suction dredger floats, excavation of the dredger pit is conducted again till the dredger pit with the depth and the area meeting requirements is excavated. Compared with the prior art, the sandbeach-staying-waiting construction method has the advantages that the time spent on entering and exiting of the dredger and pipe disassembling is saved, excavation of the dredger pit can be completed only through two days and four tides, construction efficiency is greatly improved compared with a conventional construction method, the structure of the dredger is not influenced by sandbeach staying waiting construction, and economic benefits are quite remarkable.

Description

technical field [0001] The invention relates to a construction method of a cutter suction dredger waiting on the beach. Background technique [0002] The draft of a large cutter suction dredger can reach 3.6-3.8m. During normal construction, the water depth in the soil borrowing area must meet the normal draft requirements of the ship. In recent years, with the rise of coastal land reclamation projects, the working conditions of cutter suction ship construction have become more and more complicated. The working conditions of shallow water depth in the borrow area are often encountered during construction, and even wetlands occur at low tide. It simply cannot meet the water depth requirements for normal construction of ships. For this reason, ship construction needs to wait for the tide to enter the construction point, excavate the ship nest when the tide level meets the draft, and retreat to a deeper water depth in time if the water level is insufficient. Due to the small ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02F3/88B63J2/12
CPCB63J2/12E02F3/885E02F3/907
Inventor 徐和夫王慧敏徐勇平蒋冠乔玉宝舒建华吴国强
Owner SDC WATERWAY CONSTR
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products