A prefabricated shaft wall structure and its construction method

A prefabricated assembly and well wall technology, which is applied to vertical shaft equipment, wellbore lining, water supply devices, etc., can solve the problems of long exposure time of foundation pit wall, complicated wet operation procedures, and difficulty in quality assurance. Solve the effect of water supply and slurry supply and slurry discharge for multiple equipment, and the cost is low
CN105862990BActive Publication Date: 2019-05-24SHANGHAI MECHANIZED CONSTR GRP

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
SHANGHAI MECHANIZED CONSTR GRP
Publication Date
2019-05-24

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses a prefabricated assembly well wall structure and a construction method thereof. The prefabricated assembly well wall structure is formed by splicing and assembling a plurality of prefabricated pipe pieces in the longitudinal direction and the annular direction; a plurality of prestress through holes penetrating through the upper end and the lower end, a plurality of grouting holes and a plurality of slurry discharging holes are formed in each prefabricated pipe piece at intervals; a prestress connecting element is arranged in each prestress through hole, and extends out from the upper end and the lower end of the corresponding prestress through hole; inclined inner holes are formed in two ends of the annular direction of the inner side of each prefabricated pipe piece; an inclined connecting sleeve is embedded in each inclined inner hole; and a force transmission bushing and a water stop structure are arranged between two prefabricated pipe pieces which are adjacent in the longitudinal direction and the annular direction. The prefabricated assembly well wall structure is formed by splicing the prefabricated pipe pieces; the vertical shaft foundation pit excavation enclosure exposure time is reduced; the complicated process of a wet construction work procedure is simplified; the work intensity of workers is reduced; the construction speed is high; the cost and the manufacturing price are low; the environment pollution is low; and good social effects and economic effects are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the technical field of underground building construction, in particular to a prefabricated well wall structure and a construction method thereof. Background technique

[0002] With the acceleration of the urbanization process, the urban population is highly dense, and the production and transportation are dense, which makes the contradiction of parking difficult in large and medium-sized cities such as Beijing, Shanghai, and Guangzhou increasingly prominent. Underground parking garages are a hot topic worthy of research. At present, various countries are trying their best to promote "sponge" cities, and have conducted a series of explorations on how to improve the water storage function of super-large cities. Among them, Tokyo, Japan has established the world's largest deep storage. The water pipeline project has effectively improved the water storage function of the city. At present, many large cities in my country, such as S...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More