A method for installing a chain track

An installation method and a chain-type technology, which is applied in the erection/assembly of bridges, buildings, bridge construction, etc., can solve the problems of long installation time in the air, personnel in the installation method, and great safety threats, and achieve easy on-site operation, saving personnel, and The effect of reducing security risks

Active Publication Date: 2020-03-31
CHINA RAILWAY ERJU 5TH ENG +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] The inspection and maintenance of the arch ribs of the existing upper-supported steel truss arch bridges generally adopt the method of setting tracks on the lower parallel beams, and the tracks carry maintenance trolleys; the installation method of the tracks and the lower parallel beams is to set two A winch, the steel wire rope is arranged along the track installation axis to the mid-span and loops back to the arch foot to pull the hoisting area, and a pulley is installed at each lower parallel beam to fix the steel wire rope to protect the paint surface of the bridge. At the arch foot, use a car crane to install the arch first. At the foot of the track, use the hoist to pull the track to the installation position, and use the chain hoist suspended on the upper parallel to assist in the installation of the track; this traction installation method requires a large investment in personnel and equipment, and the installation in the air takes a long time, which poses a greater threat to safety

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A method for installing a chain track
  • A method for installing a chain track
  • A method for installing a chain track

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0058] Such as Figure 1-6 Shown, the installation method of a kind of chain track of the present invention, uses a kind of chain track installation vehicle, and this installation vehicle comprises:

[0059] track laying base 1;

[0060] The running mechanism 2 is arranged on the track laying base 1, the running mechanism 2 is connected to the installed track segment 7, the track segment 7 is provided with a chain 71, and the running mechanism 2 is provided with Gear 21, the cooperation of described gear 21 and described chain 71 makes described walking mechanism 2 can move along described track segment 7, and the two ends of described track segment 7 are respectively provided with stretching mechanism 74, and described stretching The release mechanism 74 is used for tensioning, loosening, connecting and installing of the chain 71;

[0061] The driving mechanism 3 is arranged on the track laying base 1, and the driving mechanism 3 is used to drive the gear 21 to move along t...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a novel chain track installation method, which comprises the following steps: (1) marking the position of the track to be installed on a horizontal cross beam under an arch rib; B, arranging a track clasp and a track bracket at that marked position; C, lifting a track segment at the arch foot, connecting the track segment to the track support, adjusting a stretching mechanism, and connecting two adjacent chains into one body; D, hoisting a traveling mechanism and connecting the traveling mechanism to the track segment ; E, lifting a track laying base to be connected with the traveling mechanism; F, filling a track segment to be installed in a feeding mechanism when the traveling mechanism is operated to an arch foot; G, when the traveling mechanism runs to the trackarea to be installed and the feeding mechanism transports the track segment to be installed, receiving the track segment to be installed by a jacking mechanism, lifting the track segment to the trackarea to be installed to be connected to the corresponding track bracket, and adjusting the stretching mechanism to be connected to the two adjacent chains into one; H repeating steps F and G to forma complete chain track.

Description

technical field [0001] The invention relates to the technical field of bridge maintenance equipment, in particular to a method for installing a chain track. Background technique [0002] The inspection and maintenance of the arch ribs of the existing upper-supported steel truss arch bridges generally adopt the method of setting tracks on the lower parallel beams, and the tracks carry maintenance trolleys; the installation method of the tracks and the lower parallel beams is to set two A winch, the steel wire rope is arranged along the track installation axis to the mid-span and loops back to the arch foot to pull the hoisting area, and a pulley is installed at each lower parallel beam to fix the steel wire rope to protect the paint surface of the bridge. At the arch foot, use a car crane to install the arch first. At the foot of the track, the hoist is used to pull the track to the installation position, and the chain hoist suspended on the upper parallel is used to assist i...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E01D22/00E01D19/10
CPCE01D19/106E01D22/00
Inventor 周辉宁远思赵伟郜小群李友明王晓棠刘高松
Owner CHINA RAILWAY ERJU 5TH ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products