Cavern-anchor-pile combined anti-sliding reinforcing structure and construction method thereof
A technology for strengthening structures and construction methods, applied in basic structure engineering, excavation, construction, etc., can solve the problems of unsuitable use, deterioration, and reduced reliability of anchor cable structures, so as to reduce construction safety risks, improve stress state, reduce The effect of design size
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0045] Such as figure 2 with 3 As shown, a kind of tunnel-anchor-pile combination anti-sliding reinforcement structure described in this embodiment includes: tunnel structure 1, which is arranged on the main axis section of the vertical landslide, and is buried below the sliding surface 7; anchor structure 2, which is arranged on tunnel structure 1 The rock and soil mass 8 on the side of the rear edge of the landslide is fixedly connected with the tunnel structure 1; the anti-slide pile 3 is arranged in the landslide body 9 on the side below the tunnel structure 1; the tension anchor cable 4 is fixed at both ends of the tunnel structure 1 and Between the tops of the anti-slide piles 3; the construction channel 5 is set between the tunnel structure 1 and the landslide slope;
[0046] On the basis of the above, in a further preferred manner, the tunnel structure 1 is poured with reinforced concrete, the diameter is generally not less than 2.0m, and it is not less than 2m burie...
Embodiment 2
[0049] Such as figure 2 with 3As shown, the construction method described in this embodiment for forming a kind of tunnel-anchor-pile combined anti-sliding reinforcement structure as described in Embodiment 1 includes the following steps:
[0050] A. Plane positioning of the construction channel 5, excavate the construction channel 5 pile wells in sections, and set up retaining walls in sections until the bottom elevation of the tunnel structure 1;
[0051] B. Excavate the tunnel structure 1 well hole to both sides through the construction channel 5, and set up the well hole enclosure structure in sections;
[0052] C. Anchor structure 2 is constructed in the tunnel enclosure structure of tunnel structure 1, and the exposed length of anchor structure 2 in the tunnel is not less than 1.5m;
[0053] D. Plane positioning of the anti-slide pile 3, directional construction of the tension anchor cable 4 borehole at the top of the anti-slide pile 3, and the bottom of the borehole ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com