Prefabricated column segmented prefabricating and installing process
A prefabricated installation and prefabricated column technology, applied in the direction of columns, pier columns, pillars, etc., can solve the problems of high difficulty in transportation and on-site installation, achieve inconvenient installation and transportation, high practical value and promotion value, and improve installation efficiency and quality Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0026] Please refer to figure 1 , this embodiment provides a segmented prefabricated installation process for prefabricated columns. The segmented prefabricated installation process can solve the technical problem of inconvenient installation and transportation caused by the high height of prefabricated columns, and ensure the smooth installation of prefabricated columns through segmented installation; It includes the following steps:
[0027] Step 1. Prefabricated column pouring and forming: According to the overall height of the prefabricated column, it is designed in sections as an upper precast column 100 and a lower precast column 200 and poured and formed respectively, wherein the sum of the height of the upper precast column 100 and the lower precast column 200 is equal to the height of the precast column The overall design height is compatible; the corresponding precast column connectors are adapted according to the size of the upper precast column 100 and the lower pr...
Embodiment 2
[0033] Such as figure 2 As shown, this embodiment provides a corresponding installation structure for the prefabricated installation process in Embodiment 1; wherein the prefabricated column connector includes a connector body 300 corresponding to the section of the upper prefabricated column 100 and the lower prefabricated column 200, the connection A welding part is provided on the part body 300 , and the welding part is welded and connected with the connecting steel bars in the upper precast column 100 and the lower precast column 200 ; in addition, the edge of the connecting part body 300 is provided with a bolt connection hole 310 . In this way, the welded portion of the connector body 300 can be welded to the connecting steel bars on the end faces of the upper precast column 100 and the lower precast column 200 , improving the stability of the connection and the convenience of construction.
[0034] Such as figure 2 As shown, the cable-stayed connecting piece used for...