Automatic welding method for two sides of oblique conical shell in large-diameter eccentric oblique conical shell heat exchanger

By using automatic welding method and auxiliary cylinder rotation device in large diameter eccentric oblique cone shell heat exchanger, the problems of manual welding difficulty and equipment not being able to rotate are solved, efficient automatic welding of ring seams is achieved, and defect rate is reduced and Production costs improve product quality.

CN119016929APending Publication Date: 2024-11-26HARBIN BOILER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411444931.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-16
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The thickness of the ring joints on both sides of the oblique cone shell in large diameter eccentric oblique cone shell heat exchanger is thick, resulting in large amount of manual welding and low success rate, which is prone to welding defects, and the equipment cannot rotate and automatic welding cannot be performed.

Method used

The automatic welding method is adopted, by installing small-diameter and large-diameter auxiliary cylinders, the roller frame is used to realize concentric rotation of the eccentric oblique cone shell and the equipment shell, and automatic welding of the ring seam is performed, and non-destructive testing and defect repair are performed.

Benefits of technology

It greatly reduces the incidence of welding defects, improves welding quality and production efficiency, reduces production costs, and ensures product quality and production cycle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119016929A_ABST
    Figure CN119016929A_ABST
Patent Text Reader

Abstract

The invention discloses an automatic welding method for two sides of an oblique conical shell in a large-diameter eccentric oblique conical shell heat exchanger, and relates to the field of welding manufacturing. The problem that welding defects are prone to occurring when girth welding is conducted on the two ends of an existing oblique conical shell is solved. The automatic welding method comprises the following steps: positioning and spot-welding the eccentric oblique conical shell; preparing a small-caliber auxiliary cylinder and a large-caliber auxiliary cylinder; a small-caliber auxiliary cylinder is additionally arranged; automatically welding a small opening side; dismounting the small-caliber auxiliary cylinder; sleeving an equipment shell; a large-caliber auxiliary cylinder is additionally arranged; automatically welding a large opening side; and dismounting the large-caliber auxiliary cylinder. The method is used for welding the large-diameter eccentric oblique conical shell.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of welding manufacturing, and in particular to an automatic welding method for both sides of an inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger. Background Art

[0002] In the synthetic ammonia projects of the chemical industry, all of them contain large-diameter eccentric oblique cone heat exchangers with similar structures. This structure causes the center of the whole equipment to be not in the same straight line, and the equipment cannot rotate normally. The inability to rotate will make the equipment unable to be automatically welded, and the thickness of the annular seam on both sides of the eccentric oblique cone shell is relatively thick. If manual welding is used, full-position manual welding is required, the welding volume is large, the success rate is low, and welding defects are easily caused. Therefore, a new welding method is urgently needed to meet the production needs of this structure equipment. Summary of the invention

[0003] In order to solve the problem that welding defects are easy to occur during the welding of the annular seams at both ends of the existing inclined cone shell, the present invention further proposes an automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger.

[0004] The technical solution adopted by the present invention to solve the above technical problems is:

[0005] An automatic welding method for both sides of an inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger includes the following process:

[0006] Step 1: Positioning spot welding of the eccentric oblique cone shell: pair and weld the pipe system box assembly with the eccentric oblique cone shell, and fix them by spot welding after adjusting the concentricity between the pipe system box assembly and the eccentric oblique cone shell;

[0007] Step 2, preparing a small-diameter auxiliary cylinder and a large-diameter auxiliary cylinder: by measuring the outer diameter of the tube box in the eccentric oblique cone shell, determine the outer diameter of the small-diameter auxiliary cylinder, and prepare the small-diameter auxiliary cylinder; by measuring the outer diameter of the cylinder in the equipment shell, determine the outer diameter of the large-diameter auxiliary cylinder, and prepare the large-diameter auxiliary cylinder;

[0008] Step 3: Install a small-diameter auxiliary cylinder: Install a small-diameter auxiliary cylinder inside the eccentric oblique cone shell. After confirming that the pipe system box assembly and the small-diameter auxiliary cylinder are concentric, spot weld the small-diameter auxiliary cylinder and the eccentric oblique cone shell. After fixation, place the eccentric oblique cone shell, the pipe system box assembly and the small-diameter auxiliary cylinder on the roller frame, ensuring that the small-diameter auxiliary cylinder falls on the driving wheel of the roller frame and the pipe system box assembly falls on the driven wheel of the roller frame.

[0009] Step 4: Automatic welding of the small-mouth side: The driving wheel of the roller frame is driven to rotate, which drives the eccentric oblique cone shell, the pipe system box assembly and the small-diameter auxiliary cylinder to rotate synchronously. At the same time, the automatic welding machine is used to automatically weld the weld between the pipe system box assembly and the eccentric oblique cone shell step by step;

[0010] Step 5: Dismantle the small-diameter auxiliary cylinder: separate the small-diameter auxiliary cylinder from the eccentric oblique cone shell, and grind the small-diameter auxiliary cylinder for subsequent use;

[0011] Step 6: Assemble the equipment shell: assemble and weld the equipment shell and the eccentric oblique cone shell together, and fix them by spot welding after adjusting the concentricity between the equipment shell and the eccentric oblique cone shell;

[0012] Step 7. Install a large-diameter auxiliary cylinder: Install a large-diameter auxiliary cylinder on the outside of the eccentric oblique cone shell. After confirming that the equipment shell and the large-diameter auxiliary cylinder are concentric, spot weld the large-diameter auxiliary cylinder and the eccentric oblique cone shell. After fixation, lift the pipe system box assembly, the eccentric oblique cone shell, the large-diameter auxiliary cylinder and the equipment shell as a whole, adjust the distance between the driving wheel and the driven wheel of the roller frame, and ensure that the equipment shell falls on the driving wheel and the large-diameter auxiliary cylinder falls on the driven wheel;

[0013] Step 8: Automatic welding of the large-mouth side: The driving wheel of the roller frame is driven to rotate, driving the pipe system box assembly, the eccentric oblique cone shell, the large-diameter auxiliary cylinder and the equipment shell to rotate synchronously, and at the same time, the automatic welding machine is used to automatically weld the weld between the equipment shell and the eccentric oblique cone shell step by step;

[0014] Step 9. Dismantle the large-diameter auxiliary cylinder: separate the large-diameter auxiliary cylinder from the eccentric oblique cone shell, and grind the large-diameter auxiliary cylinder for subsequent use.

[0015] Furthermore, in the step 2, the preparation methods of the small-diameter auxiliary cylinder and the large-diameter auxiliary cylinder are both carried out by blanking, rolling and welding.

[0016] Furthermore, in step 4, after completing the automatic welding of the small opening side, the welding part needs to be subjected to non-destructive testing, and subsequent steps can be carried out only after the test is qualified.

[0017] Furthermore, for products that fail the inspection, the welding defect location is repaired, and after the repair, the welding part is subjected to non-destructive testing. After the inspection is qualified, the subsequent steps are carried out. If the inspection fails, the repair process is repeated until the inspection is qualified.

[0018] Furthermore, the repair process for the welding defect position includes cleaning, gas cutting, grinding and repair welding.

[0019] Furthermore, in step five, the small-diameter auxiliary cylinder is separated from the eccentric oblique cone shell by gas cutting and grinding.

[0020] Furthermore, in step eight, after completing the automatic welding of the large-mouth side, it is necessary to perform non-destructive testing on the welding part, and then proceed to the subsequent steps after the test is qualified.

[0021] Furthermore, for products that fail the inspection, the welding defect location is repaired, and after the repair, the welding part is subjected to non-destructive testing. After the inspection is qualified, the subsequent steps are carried out. If the inspection fails, the repair process is repeated until the inspection is qualified.

[0022] Furthermore, the repair process for the welding defect position includes cleaning, gas cutting, grinding and repair welding.

[0023] Furthermore, in step nine, the large-diameter auxiliary cylinder is separated from the eccentric oblique cone shell by gas cutting and grinding.

[0024] Compared with the prior art, the present invention has the following beneficial effects:

[0025] Nearly 100 such devices have been produced by using the method of automatic welding on both sides of the inclined cone shell of a large-diameter eccentric inclined cone shell heat exchanger, which greatly reduces the defects caused by the welding of the circumferential seams on both sides of the inclined cone shell, thereby reducing production costs.

[0026] The method for realizing automatic welding on both sides of the inclined cone shell of a large-diameter eccentric inclined cone shell heat exchanger is convenient to operate, has wide applicability, simple structure, improves work efficiency, and ensures production cycle and product quality. The invention mainly solves the need for automatic welding on both sides of the inclined cone shell of a large-diameter eccentric inclined cone shell heat exchanger. Secondly, the invention has played a good role in the production process and improved the welding quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the structure of the automatic welding of the small opening side of the eccentric oblique cone shell in the present invention;

[0028] Figure 2 It is a structural schematic diagram of the automatic welding of the large mouth side of the eccentric oblique cone shell in the present invention. DETAILED DESCRIPTION

[0029] In order to make the technical problems, technical solutions and beneficial effects solved by the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0030] Specific implementation method 1: Combination Figure 1 to Figure 2 This embodiment describes an automatic welding method for both sides of the oblique cone shell in a large-diameter eccentric oblique cone shell heat exchanger, which includes the following process:

[0031] Step 1: Positioning and spot welding of the eccentric oblique cone shell 2: Pair and weld the pipe system box assembly 1 and the eccentric oblique cone shell 2, and fix them by spot welding after adjusting the pipe system box assembly 1 and the eccentric oblique cone shell 2 to be concentric;

[0032] Step 2, preparing the small-diameter auxiliary cylinder 3 and the large-diameter auxiliary cylinder 7: by measuring the outer diameter of the tube box in the eccentric oblique cone shell 2, the outer diameter of the small-diameter auxiliary cylinder 3 is determined, and the small-diameter auxiliary cylinder 3 is prepared; by measuring the outer diameter of the cylinder in the equipment shell 6, the outer diameter of the large-diameter auxiliary cylinder 7 is determined, and the large-diameter auxiliary cylinder 7 is prepared;

[0033] Step 3, installing the small-diameter auxiliary cylinder 3: install the small-diameter auxiliary cylinder 3 inside the eccentric oblique cone shell 2, and after confirming that the pipe system box assembly 1 and the small-diameter auxiliary cylinder 3 are concentric, spot weld the small-diameter auxiliary cylinder 3 and the eccentric oblique cone shell 2, and after fixation, place the eccentric oblique cone shell 2, the pipe system box assembly 1 and the small-diameter auxiliary cylinder 3 on the roller frame, ensuring that the small-diameter auxiliary cylinder 3 falls on the driving wheel 4 of the roller frame, and the pipe system box assembly 1 falls on the driven wheel 5 of the roller frame;

[0034] Step 4: Automatic welding of the small-mouth side: The driving wheel 4 of the driving roller frame is driven to rotate, driving the eccentric oblique cone shell 2, the pipe system box assembly 1 and the small-diameter auxiliary cylinder 3 to rotate synchronously, and at the same time, the weld between the pipe system box assembly 1 and the eccentric oblique cone shell 2 is automatically welded step by step by using an automatic welding machine;

[0035] Step 5, dismantling the small-diameter auxiliary cylinder 3: separating the small-diameter auxiliary cylinder 3 from the eccentric oblique cone shell 2, and grinding the small-diameter auxiliary cylinder 3 for subsequent use;

[0036] Step 6, assembling the equipment housing 6: assembling and welding the equipment housing 6 and the eccentric oblique cone shell 2, and spot welding and fixing them after adjusting the concentricity between the equipment housing 6 and the eccentric oblique cone shell 2;

[0037] Step 7, installing a large-diameter auxiliary cylinder 7: Install a large-diameter auxiliary cylinder 7 on the outside of the eccentric oblique cone shell 2. After confirming that the equipment housing 6 and the large-diameter auxiliary cylinder 7 are concentric, spot weld the large-diameter auxiliary cylinder 7 and the eccentric oblique cone shell 2. After fixation, lift the pipe system box assembly 1, the eccentric oblique cone shell 2, the large-diameter auxiliary cylinder 7 and the equipment housing 6 as a whole, adjust the distance between the driving wheel 4 and the driven wheel 5 of the roller frame, and ensure that the equipment housing 6 falls on the driving wheel 4 and the large-diameter auxiliary cylinder 7 falls on the driven wheel 5;

[0038] Step 8, automatic welding of the large-mouth side: the driving wheel 4 of the driving roller frame is rotated, driving the pipe system box assembly 1, the eccentric oblique cone shell 2, the large-diameter auxiliary cylinder 7 and the equipment shell 6 to rotate synchronously, and at the same time, the automatic welding machine is used to automatically weld the weld between the equipment shell 6 and the eccentric oblique cone shell 2 step by step;

[0039] Step nine, dismantling the large-diameter auxiliary cylinder 7: separating the large-diameter auxiliary cylinder 7 from the eccentric oblique cone shell 2, and grinding the large-diameter auxiliary cylinder 7 for subsequent use.

[0040] This method achieves concentricity on both sides by adding auxiliary cylinders on both sides, and after concentricity, the equipment is rotated for automatic welding of the circumferential seam, thereby reducing welding defects. The method of realizing automatic welding on both sides of the inclined cone shell of a large-diameter eccentric inclined cone shell heat exchanger uses two steel plate rolled cylinders and is realized through a series of assembly schemes. The cylinder in this method can be changed according to the different diameters of the equipment to assist in rotation. The automatic welding on both sides of the eccentric inclined cone shell is solved, ensuring the production quality and cycle of the product.

[0041] The automatic welding method can realize automatic welding on both sides of a large-diameter eccentric oblique cone shell.

[0042] The automatic welding method consists of an assembly sequence and two cylinders of different diameters.

[0043] The two cylinders of different diameters in the automatic welding method can be varied according to the specific size of the equipment.

[0044] The automatic welding method has the functions of fixing, supporting and assisting rotation.

[0045] Specific implementation method 2: Combination Figure 1 to Figure 2 To illustrate this embodiment, in step 2 of this embodiment, the preparation methods of the small-diameter auxiliary cylinder 3 and the large-diameter auxiliary cylinder 7 are both prepared by blanking, rolling and welding.

[0046] The undisclosed technical features in this embodiment are the same as those in the first embodiment.

[0047] Specific implementation method three: Combination Figure 1 to Figure 2 To explain this embodiment, in step 4 of this embodiment, after completing the automatic welding of the small opening side, it is necessary to perform non-destructive testing on the welding part, and then proceed to the subsequent steps after passing the test.

[0048] The undisclosed technical features in this embodiment are the same as those in the first embodiment.

[0049] Specific implementation method four: Combination Figure 1To explain this embodiment, for products that fail the inspection, the welding defect position is repaired, and the welding part is subjected to non-destructive testing after the repair. After the inspection is qualified, the subsequent steps are carried out. If the inspection fails, the repair process is repeated until the inspection is qualified.

[0050] The undisclosed technical features in this embodiment are the same as those in the third embodiment.

[0051] Specific implementation method five: Combination Figure 1 To illustrate this embodiment, the repair process for the welding defect position in this embodiment includes cleaning, gas cutting, grinding and repair welding.

[0052] The undisclosed technical features in this embodiment are the same as those in the fourth embodiment.

[0053] Specific implementation method six: Combination Figure 1 To explain this embodiment, in step five of this embodiment, the small-diameter auxiliary cylinder 3 is separated from the eccentric oblique cone shell 2 by gas cutting and grinding.

[0054] The undisclosed technical features in this embodiment are the same as those in the first embodiment.

[0055] Specific implementation method seven: Combination Figure 2 To explain this embodiment, in step eight of this embodiment, after completing the automatic welding of the large-mouth side, it is necessary to perform non-destructive testing on the welding part, and then proceed to the subsequent steps after passing the test.

[0056] The undisclosed technical features in this embodiment are the same as those in the first embodiment.

[0057] Specific implementation method eight: Combination Figure 2 To explain this embodiment, for products that fail the inspection, the welding defect position is repaired, and the welding part is subjected to non-destructive testing after the repair. After the inspection is qualified, the subsequent steps are carried out. If the inspection fails, the repair process is repeated until the inspection is qualified.

[0058] The undisclosed technical features in this embodiment are the same as those in the seventh embodiment.

[0059] Specific implementation method nine: Combination Figure 2 To illustrate this embodiment, the repair process for the welding defect position in this embodiment includes cleaning, gas cutting, grinding and repair welding.

[0060] The undisclosed technical features in this embodiment are the same as those in the eighth embodiment.

[0061] Specific implementation method ten: Combination Figure 2 To explain this embodiment, in step nine of this embodiment, the large-diameter auxiliary cylinder 7 is separated from the eccentric oblique cone shell 2 by gas cutting and grinding.

[0062] The undisclosed technical features in this embodiment are the same as those in the first embodiment.

[0063] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. An automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger. Features: The method comprises the following steps: Step 1: Positioning and spot welding of the eccentric oblique cone shell (2): the pipe system box assembly (1) and the eccentric oblique cone shell (2) are matched and welded, and after the pipe system box assembly (1) and the eccentric oblique cone shell (2) are adjusted to be concentric, spot welding is performed to fix them; Step 2, preparing a small-diameter auxiliary cylinder (3) and a large-diameter auxiliary cylinder (7): by measuring the outer diameter of the tube box in the eccentric oblique cone shell (2), the outer diameter of the small-diameter auxiliary cylinder (3) is determined, and the small-diameter auxiliary cylinder (3) is prepared; by measuring the outer diameter of the cylinder in the equipment shell (6), the outer diameter of the large-diameter auxiliary cylinder (7) is determined, and the large-diameter auxiliary cylinder (7) is prepared; Step 3, installing a small-diameter auxiliary cylinder (3): installing a small-diameter auxiliary cylinder (3) inside the eccentric oblique cone shell (2), and after confirming that the pipe system box assembly (1) and the small-diameter auxiliary cylinder (3) are concentric, spot welding is performed between the small-diameter auxiliary cylinder (3) and the eccentric oblique cone shell (2), and after fixing, the eccentric oblique cone shell (2), the pipe system box assembly (1) and the small-diameter auxiliary cylinder (3) are placed on a roller frame, ensuring that the small-diameter auxiliary cylinder (3) falls on the driving wheel (4) of the roller frame, and the pipe system box assembly (1) falls on the driven wheel (5) of the roller frame; Step 4: Automatic welding of the small-mouth side: The driving wheel (4) of the driving roller frame is driven to rotate, thereby driving the eccentric oblique cone shell (2), the pipe system box assembly (1) and the small-diameter auxiliary cylinder (3) to rotate synchronously, and at the same time, the weld between the pipe system box assembly (1) and the eccentric oblique cone shell (2) is automatically welded step by step by using an automatic welding machine; Step 5: Dismantle the small-diameter auxiliary cylinder (3): separate the small-diameter auxiliary cylinder (3) from the eccentric oblique cone shell (2), and grind the small-diameter auxiliary cylinder (3) for subsequent use; Step 6, assembling the device housing (6): assembling and welding the device housing (6) and the eccentric oblique cone housing (2) together, and spot welding and fixing them after adjusting the concentricity between the device housing (6) and the eccentric oblique cone housing (2); Step 7, installing a large-diameter auxiliary cylinder (7): installing a large-diameter auxiliary cylinder (7) on the outside of the eccentric oblique cone shell (2), and after confirming that the equipment housing (6) and the large-diameter auxiliary cylinder (7) are concentric, spot-welding the large-diameter auxiliary cylinder (7) and the eccentric oblique cone shell (2) to fix them. After fixing, hoist the pipe system box assembly (1), the eccentric oblique cone shell (2), the large-diameter auxiliary cylinder (7) and the equipment housing (6) as a whole, and adjust the distance between the driving wheel (4) and the driven wheel (5) of the roller frame to ensure that the equipment housing (6) falls on the driving wheel (4) and the large-diameter auxiliary cylinder (7) falls on the driven wheel (5); Step 8: Automatic welding of the large-mouth side: The driving wheel (4) of the roller frame is driven to rotate, so as to drive the pipe system box assembly (1), the eccentric oblique cone shell (2), the large-diameter auxiliary cylinder (7) and the equipment shell (6) to rotate synchronously, and at the same time, the weld between the equipment shell (6) and the eccentric oblique cone shell (2) is automatically welded step by step by using an automatic welding machine; Step 9, dismantling the large-diameter auxiliary cylinder (7): separate the large-diameter auxiliary cylinder (7) from the eccentric oblique cone shell (2), and grind the large-diameter auxiliary cylinder (7) for subsequent use.

2. According to claim 1, an automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger, Features: In the step 2, the small-diameter auxiliary cylinder (3) and the large-diameter auxiliary cylinder (7) are prepared by cutting, rolling and welding.

3. According to claim 1, an automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger, Features: After the automatic welding of the small opening side is completed in step 4, the welding part needs to be subjected to non-destructive testing, and the subsequent steps can be carried out after the test is qualified.

4. According to claim 3, an automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger, Features: For products that fail the inspection, the welding defect locations are repaired, and then non-destructive testing is performed on the welding parts after the repair. After passing the inspection, the subsequent steps are carried out. If the inspection fails, the repair process is repeated until the inspection passes.

5. According to claim 4, an automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger, Features: The repair processes for welding defects include cleaning, gas cutting, grinding and repair welding.

6. According to claim 1, an automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger, Features: In the step five, the small-caliber auxiliary cylinder (3) is separated from the eccentric oblique cone shell (2) by means of gas cutting and grinding.

7. According to claim 1, an automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger, Features: After the automatic welding of the large-mouth side is completed in step eight, the welding part needs to be subjected to nondestructive testing, and the subsequent steps can be carried out only after the test is qualified.

8. According to claim 7, an automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger, Features: For products that fail the inspection, the welding defect locations are repaired, and then non-destructive testing is performed on the welding parts after the repair. After passing the inspection, the subsequent steps are carried out. If the inspection fails, the repair process is repeated until the inspection passes.

9. An automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger according to claim 8, Features: The repair processes for welding defects include cleaning, gas cutting, grinding and repair welding.

10. The automatic welding method for both sides of the inclined cone shell in a large-diameter eccentric inclined cone shell heat exchanger according to claim 1, Features: In the step nine, the large-diameter auxiliary cylinder (7) is separated from the eccentric oblique cone shell (2) by means of gas cutting and grinding.