Rapid warm milling device of coal mill
By setting up a heater, a blower, a primary fan and an air preheater in the coal mill, a complete air duct is formed, and the temperature sensor is used to control the temperature of the coal mill, the problem of long heating time in the existing technology is solved, and the realization of the realization of the realization of the heating time. The boiler start-up time and cost reduction are reduced.
Patent Information
- Application Number
- CN202420478986.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-12
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-03-12
AI Technical Summary
During the start-up of the existing 135MW direct blowing coal pulverized boiler, the long warm grinding time leads to a large consumption of fuel, coal and steam, which increases the boiler start-up cost.
A rapid heating device for coal mills is designed, including a heater, a blower, a primary fan, an air preheater and a sealed air duct, etc., and the rapid preheating of the coal mills is achieved by forming a complete air duct and temperature sensor. and temperature control to shorten the warm grinding time.
It greatly shortens the boiler start time, saves fuel and air exhaust, reduces startup costs, and reduces workload for staff.
Smart Images

Figure CN222068880U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of boiler equipment, in particular to a coal mill rapid warming device. Background Art
[0002] In a coal-fired boiler, the pulverizing system is a very important system in boiler combustion. It is responsible for the preparation and transportation of coal powder in the boiler combustion system. It not only provides coal powder with qualified fineness for the boiler, but also provides appropriate air volume and air temperature for the transportation of coal powder.
[0003] At present, in the existing technology, the startup of a 135MW direct-blowing pulverized coal boiler is carried out according to the startup process of "purging - adding oil - adding pulverized coal - and adding steam". A hot start takes 3.5 to 4 hours, mainly using the heat of an oil gun for warming up, which results in a long warming up time and a large consumption of fuel oil, coal and steam, thereby increasing the startup cost of the boiler. Utility Model Content
[0004] Aiming at the deficiencies of the prior art, the utility model develops a coal mill rapid warming device, which can rapidly warm the mill and save operating steps, effectively reducing boiler startup costs and reducing the workload of staff.
[0005] The technical solution to the technical problem solved by the utility model is: a coal mill rapid warming device, comprising a heater and a coal mill, and also comprising an air supply fan, a primary fan and an air preheater, the air outlet of the heater is connected to the first air inlet of the air preheater through a cold air duct, the air supply fan is arranged on the cold air duct, the cold air duct between the air supply fan and the air preheater is connected to the coal mill through a cold primary air duct, the primary fan is arranged on the cold primary air duct, the cold primary air duct between the primary fan and the coal mill is connected to the second air inlet of the air preheater through a cold primary air branch pipe, and the second air outlet of the air preheater is connected to the coal mill through a hot primary air duct.
[0006] As an optimization, the cold primary air branch pipe is connected to the coal mill through a sealed air duct, and a sealed fan is provided on the sealed air duct. The sealing requirements of the coal mill are met by setting the sealed air duct and the sealed fan.
[0007] As an optimization, the separator outlet of the coal mill is connected to the boiler through a coal powder pipe. The coal powder pipe can serve as an air duct when the mill is warm, and can send the coal powder produced by the coal mill to the boiler when it is officially running.
[0008] As an optimization, a first temperature sensor is provided at the connection between the hot primary air duct and the coal mill, and a second temperature sensor is provided at the connection between the coal mill separator outlet and the coal powder pipe. By providing the first temperature sensor and the second temperature sensor, the temperature of the coal mill air inlet and the separator outlet can be detected to judge the warm grinding condition, thereby stopping the warm grinding, reducing the boiler startup cost, achieving the purpose of reducing costs and increasing efficiency, and reducing the probability of misoperation of important equipment.
[0009] As an optimization, the first air outlet of the air preheater is connected to the boiler through a pipeline, so as to provide air for the combustion operation of the boiler.
[0010] As an optimization, the exhaust port of the boiler is equipped with an induced draft fan. By setting up the induced draft fan, it cooperates with the blower and primary fan to extract air outward during the warm grinding process, thereby improving the warm grinding efficiency.
[0011] Compared with the prior art, the utility model has the following beneficial effects:
[0012] By setting up a heater, the air can be preliminarily heated to improve the air heating efficiency; by setting up a blower, the air passing through the heater can be pressurized and transported downward; by setting up a primary fan, the air can be further pressurized and transported; by setting up an air preheater, the air can be heated to form hot primary air, and a complete air duct can be formed by cooperating with the cold air duct, the cold primary air duct, the cold primary air branch pipe and the hot primary air duct. By taking advantage of the trial operation opportunity before the boiler is started, the hot air door, the mixing air door and the separator outlet door of the coal mill can be opened when the primary fan is started for trial operation to preheat the coal mill. The outlet temperature of the coal mill separator can be quickly increased, which can greatly shorten the oil warming time, save fuel, and save steam exhaust to the air. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of an embodiment of the utility model.
[0014] In the figure, 1 is a heater; 2 is a coal mill; 3 is a blower; 4 is a primary fan; 5 is an air preheater; 6 is a cold air duct; 7 is a cold primary air duct; 8 is a cold primary air branch pipe; 9 is a hot primary air duct; 10 is a sealed air duct; 11 is a sealed fan; 12 is a pulverized coal pipe; 13 is a boiler; 14 is a first temperature sensor; 15 is a second temperature sensor; and 16 is an induced draft fan. DETAILED DESCRIPTION
[0015] In order to clearly illustrate the technical features of the present invention, the present invention is described in detail below through specific implementation methods and in conjunction with the accompanying drawings.
[0016] Example 1
[0017] Figure 1 An embodiment of the present utility model is as follows: Figure 1As shown, a coal mill rapid warming device includes a heater 1 and a coal mill 2, and also includes an air supply fan 3, a primary air fan 4 and an air preheater 5. The air outlet of the heater 1 is connected to the first air inlet of the air preheater 5 through a cold air duct 6. The air supply fan 3 is arranged on the cold air duct 6. The cold air duct 6 between the air supply fan 3 and the air preheater 5 is connected to the coal mill 2 through a cold primary air duct 7. The primary air fan 4 is arranged on the cold primary air duct 7. The cold primary air duct 7 between the primary air fan 4 and the coal mill 2 is connected to the second air inlet of the air preheater 5 through a cold primary air branch pipe 8. The second air outlet of the air preheater 5 is connected to the coal mill 2 through a hot primary air duct 9.
[0018] By setting up the heater 1, the air can be preliminarily heated to improve the air heating efficiency; by setting up the blower 3, the air passing through the heater 1 can be pressurized and transported downward; by setting up the primary fan 4, the air can be further pressurized and transported; by setting up the air preheater 5, the air can be heated to form hot primary air, and a complete air duct is formed by cooperating with the cold air duct 6, the cold primary air duct 7, the cold primary air branch pipe 8 and the hot primary air duct 9. By taking advantage of the trial operation opportunity before the boiler is started, the hot air door, the mixing air door and the separator outlet door of the coal mill 2 are opened when the primary fan 4 is started for trial operation to preheat the coal mill 2. The separator outlet temperature of the coal mill 2 can be increased to above 65°C, which greatly shortens the oil warming time, shortens the boiler start-up time by 1.5 hours, saves 1.5T of fuel oil, and saves 120T of exhaust steam to the air.
[0019] The cold primary air branch pipe 8 is connected to the coal mill 2 through a sealed air duct 10, and a sealed fan 11 is provided on the sealed air duct 10. The sealing requirement of the coal mill 2 is met by providing the sealed air duct 10 and the sealed fan 11.
[0020] The separator outlet of the coal mill 2 is connected to the boiler 13 through the coal powder pipe 12. By setting the coal powder pipe 12, it can serve as an air duct during warm-up, and the coal powder produced by the coal mill 2 can be sent to the boiler 13 during formal operation.
[0021] A first temperature sensor 14 is provided at the connection between the hot primary air duct 9 and the coal mill 2, and a second temperature sensor 15 is provided at the connection between the separator outlet of the coal mill 2 and the pulverized coal pipe 12. By providing the first temperature sensor 14 and the second temperature sensor 15, the temperature of the air inlet and the separator outlet of the coal mill 2 can be detected, the warm grinding condition can be judged, and the warm grinding can be stopped, the boiler startup cost can be reduced, the purpose of reducing cost and increasing efficiency can be achieved, and the probability of misoperation of important equipment can be reduced.
[0022] The first air outlet of the air preheater 5 is connected to the boiler 13 through a pipeline, so as to provide air for the combustion operation of the boiler 13.
[0023] The exhaust port of the boiler 13 is provided with an induced draft fan 16. By providing the induced draft fan 16, the blower 3 and the primary fan 4 are coordinated to extract air outward during the warm grinding process, thereby improving the warm grinding efficiency.
[0024] During use, after the boiler 13 is overhauled, in order to ensure the one-time safe start-up of the boiler 13, it is necessary to test-run the 6KV equipment induced draft fan 16, the blower 3, and the primary fan 4; during the test run, start the induced draft fan 16, the blower 3, the primary fan 4, the sealed fan 11, the sealed air electric door of the coal mill 2, the separator of the coal mill 2, the outlet plug door of the coal mill 2, the mixing air door of the coal mill 2, the hot air door of the coal mill 2, the hot air regulating door opening to 100%, the heater 1 and the air preheater 5. The air enters the cold air duct 6 after preliminary heating and pressurization by the heater 1 and the blower 3, enters the cold primary air branch 8 through the cold primary air duct 7 and the pressurization of the primary fan 4, and then enters the coal mill 2 after heating by the air preheater 5 and the hot primary air duct 9. Warm grinding is carried out, and finally the coal powder is discharged by the induced draft fan 16 through the coal powder pipe 12 and the boiler 13; when the second temperature sensor 15 detects that the separator outlet temperature of the coal mill 2 reaches 65-85°C, the warm grinding is completed, the air door of the coal mill 2 is closed, the primary fan 4 is stopped, and the boiler 13 is adjusted to meet the purging condition as soon as possible; after the purging conditions are met, purging, oil addition, primary fan 4 is started, the fan 11 is sealed, and the air door of the coal mill 2 is opened to warm the coal mill 2 again. At this time, the separator outlet temperature of the coal mill 2 has met the starting conditions, the coal mill 2 can be started smoothly, and the steam connection time of the boiler 13 is shortened; the utility model can greatly shorten the oil addition warm grinding time, shorten the boiler start-up time by 1.5 hours, save 1.5T of fuel oil, save 120T of air exhaust steam, effectively reduce the start-up cost of the boiler 13, and reduce the workload of the staff.
[0025] The descriptions of the orientation or relative position relationship of the structure in the present invention, such as the orientation or relative position relationship indicated by "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc., are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the structure referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
Claims
1. A coal mill rapid warming device, comprising a warming fan (1) and a coal mill (2), characterized in that: It also includes an air supply fan (3), a primary air fan (4) and an air preheater (5); the air outlet of the warm air fan (1) is connected to the first air inlet of the air preheater (5) through a cold air pipe (6); the air supply fan (3) is arranged on the cold air pipe (6); the cold air pipe (6) between the air supply fan (3) and the air preheater (5) is connected to the coal mill (2) through a cold primary air pipe (7); the primary air fan (4) is arranged on the cold primary air pipe (7); the cold primary air pipe (7) between the primary air fan (4) and the coal mill (2) is connected to the second air inlet of the air preheater (5) through a cold primary air branch pipe (8); and the second air outlet of the air preheater (5) is connected to the coal mill (2) through a hot primary air pipe (9).
2. The coal mill rapid warming device according to claim 1 is characterized in that: The cold primary air branch pipe (8) is connected to the coal mill (2) via a sealed air duct (10), and a sealed air fan (11) is provided on the sealed air duct (10).
3. The coal mill rapid warming device according to claim 2 is characterized in that: The separator outlet of the coal mill (2) is connected to the boiler (13) via a pulverized coal pipe (12).
4. The coal mill rapid warming device according to claim 3 is characterized in that: A first temperature sensor (14) is provided at the connection between the hot primary air duct (9) and the coal mill (2), and a second temperature sensor (15) is provided at the connection between the separator outlet of the coal mill (2) and the coal powder pipe (12).
5. The coal mill rapid warming device according to claim 4 is characterized in that: The first air outlet of the air preheater (5) is connected to the boiler (13) through a pipeline.
6. The coal mill rapid warming device according to any one of claims 1 to 5, characterized in that: An induced draft fan (16) is provided at the exhaust port of the boiler (13).