Method for correcting and resetting blast furnace body
A reset method and blast furnace technology, applied in blast furnaces, blast furnace details, blast furnace parts and other directions, can solve problems such as rise or inclination, long construction period, complex process, etc., and achieve the effect of eliminating rise and inclination and shortening construction period
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2013-06-12
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to a deflection correction and reset method for a blast furnace body applied in the blast furnace overhaul process. Background technique
[0002] In the prior art, after the blast furnace has been used for a period of time, the furnace body of the blast furnace rises and tilts due to damage to the furnace bottom, which will affect the normal operation of the blast furnace. At this time, it is necessary to correct and reset the blast furnace. The entire blast furnace body is replaced, and the replacement methods include in-situ sporadic installation after the furnace body is dismantled, integral push type, and off-site reconstruction type. The integral push type is to remove the old furnace body first, and then transport the new furnace body to the furnace foundation of the original furnace body by means of translation. For example, Chinese patent 98125169.2 discloses a blast furnace overhaul and refurbishment push technology and d...
Examples
Embodiment Construction
[0047] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0048] Such as Figure 1 to Figure 7 As shown, the deflection correction and reset method for a blast furnace body includes the following steps:
[0049] A. Divide the blast furnace on the furnace base 7 into a furnace bottom 6 and an upper furnace body 5, and fix the upper furnace body 5 after being lifted by a lifting mechanism;
[0050] B, the furnace bottom 6 on the furnace foundation 7 is removed;
[0051] C. Determine the center point of the theoretical furnace bottom and the theoretical furnace bottom elevation on the furnace foundation 7;
[0052] D, install a new furnace bottom 23 on the furnace foundation 7 according to the theoretical furnace bottom central point determined in step C and the theoretical furnace bottom elevation;
[0053] E. Determine the offset distance between the orthographic projection of the top center of the ...