Mining planning method of accumulated bauxite multi-mining area
A bauxite and planning technology, applied in the field of mining, can solve problems such as fuzzy variables, difficult objective functions, and no solution, and achieve the effect of reducing the number of variables and reducing complexity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0049] A mining planning method for multiple mining areas of accumulation-type bauxite. The mining planning factors include: transportation distance, stope mineable volume, ore supply requirements, and other specific production requirements, etc. For specific logic diagrams, see figure 1 . The method of this embodiment specifically includes the following steps:
[0050] The first step: according to the planned target value (including ore volume, grade and ore content rate), take the ore unloading platform as the target point, and take the minimum total haul distance as the target to select stopes according to the distance of the haul distance (on a main road The order from near to far is selected according to the principle that the annual average transportation distance increases year by year; stopes include stopes automatically selected by the system and / or stopes designated by production management personnel; when re-selecting stopes, a mine can be used A stope with a large...
Embodiment 2
[0101] By the method of embodiment 1, carry out data test application, the result of application is as follows:
[0102] The stope data available for planning before calculation is shown in Table 1:
[0103] Table 1 Statistical table of stope data
[0104] stope number
[0105] Set target value: monthly target ore volume is 500,000 tons, constraints: (Al 2 o 3 (%)) A1=59%, (Al / Si) A2=12.5, A3=13.5, wherein number 26-2-84 is the stope that designates mining and finishes, and the result calculated by the method of the present invention is as table 2:
[0106] Table 2 Calculation results
[0107] Planned mining stope number
[0108] In the end, the actual mining qualified ore volume is 498,521.04 tons (the actual mining qualified ore volume of the five stopes is summed), and the difference is 1478.96 tons. The general method is to increase the target ore volume for the next month to compensate, or it can be Compensation shall be carried out in other ways, ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com