Novel high-pressure prefabricated cabin bus bridge and wiring method thereof

A technology of prefabricated cabins and busbar bridges, applied in the directions of busbar/circuit layout, electrical components, substation/switch layout details, etc., can solve the problem of increasing the cost of prefabricated cabin frames, failing to meet the height limit requirements of road transportation, and failing to complete small busbars on top of cabinets Maintenance and other issues

Inactive Publication Date: 2020-12-15
QINGDAO TGOOD ELECTRIC
View PDF16 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The existing modular 10kV prefabricated cabin and 35kV prefabricated cabin high-voltage cabinet adopt double-row arrangement, and the busbar connection of the two rows is designed with an overhead busbar bridge. Adding 1.5 meters to the foundation of the bridge does not meet the height limit requirements of road transportation, and greatly increases the cost of the prefabricated cabin frame; in addition, in the prior art, the busbar bridge is on the top of the high-voltage cabinet, and the maintenance of the small busbar on the top of the cabinet cannot be completed

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Novel high-pressure prefabricated cabin bus bridge and wiring method thereof
  • Novel high-pressure prefabricated cabin bus bridge and wiring method thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0023] In order to understand the above-mentioned purposes, features and advantages of the present application more clearly, the following in conjunction with the attached Figure 1-2 and specific embodiments to further describe the present application in detail. It should be noted that, under the condition of not conflicting with each other, the embodiments of the present application and the features in the embodiments can be combined with each other.

[0024] A new type of high-pressure prefabricated cabin busbar bridge, including a side connecting frame 4 and a bottom connecting frame 5, both of which are frame structures and fully spliced ​​connections; the bottom connecting frame 5 is located inside the bottom foundation frame 3 of the high-pressure prefabricated cabin 1 , the side connecting frame 4 is located on one side of the high-voltage cabinet 2, passes through the bottom plate of the high-pressure prefabricated cabin 1, and is connected to the bottom connecting fr...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a novel high-voltage prefabricated cabin bus bridge and a wiring method thereof, and the novel high-voltage prefabricated cabin bus bridge comprises a side connecting frame anda bottom connecting frame, which are both of a frame structure and are in full-splicing connection; and the bottom connecting frame is located in a bottom foundation frame of the high-pressure prefabricated cabin, and the side connecting frame is located on one side edge of the high-pressure cabinet and penetrates through a bottom plate of the high-pressure prefabricated cabin to be connected withthe bottom connecting frame. The prefabricated cabin has the advantages that no bus bridge exists in the prefabricated cabin, the overall attractiveness in the cabin is improved, meanwhile, no bus bridge exists at the top of the prefabricated cabin operation channel, the height of the prefabricated cabin is reduced, the road transportation requirement is met, the prefabricated cabin cost can be reduced, and the cabinet top small bus overhaul problem is solved.

Description

technical field [0001] The invention belongs to the field of high-voltage prefabricated cabin equipment, and in particular relates to a novel high-voltage prefabricated cabin bus bridge and a wiring method thereof. Background technique [0002] In order to respond to the development needs of the State Grid intelligent substation, the new generation of intelligent substation meets the characteristics of high system integration, reasonable layout, and miniaturization, which can reduce the equipment footprint and facilitate on-site maintenance. [0003] The existing modular 10kV prefabricated cabin and 35kV prefabricated cabin high-voltage cabinet adopt double-row arrangement, and the busbar connection of the two rows is designed with an overhead busbar bridge. Adding 1.5 meters to the foundation of the bridge does not meet the height limit requirements of road transportation, and greatly increases the cost of the prefabricated cabin frame; in addition, in the prior art, the bu...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): H02B1/20H02B1/22
CPCH02B1/207H02B1/22
Inventor 吕东明杨清清高美华生瑞东程子洳
Owner QINGDAO TGOOD ELECTRIC
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products