Method of tracking project progress automatically

A technology for project progress and automatic tracking, which is applied in the use of stored programs for program control, special data processing applications, instruments, etc., and can solve problems such as unfavorable control of R&D cycle and time, low accuracy, and unclear basis.

Inactive Publication Date: 2004-06-23
INVENTEC CORP
View PDF0 Cites 7 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] However, as far as the existing technology is concerned, there is no method that can accurately provide the overall progress of the project. Often, the person in charge of each specific task only pays attention to the progress of his own subtasks, and then reports to the general responsible person respectively. The progress of the overall project can only be roughly estimated based on the progress of each specific task
However, the basis for this kind of estimation is often unclear and the accuracy is not high, which is very unfavorable to the development cycle and time control of the entire project.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method of tracking project progress automatically
  • Method of tracking project progress automatically
  • Method of tracking project progress automatically

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0013] The present invention illustrates the concrete feasibility of this method with a preferred embodiment, with reference to figure 1 , is the computer-executed project progress automatic tracking method flow chart proposed by the present invention, and its description is as follows: first, obtain the progress R of the current task and the weight W of the task (step 101), and then calculate with R*W The task completion situation accounts for the ratio of the overall progress (step 102), judges whether all task calculations end (step 103), if not, then obtains next task and repeats last calculation step (step 104); The proportions of the overall progress are summed to obtain the overall progress of the project (step 105), and this process ends. Among them, the acquisition of the weight value can be designed to be related to the construction period. The specific steps are: first, determine the total construction period of the project; then, input the construction period of ea...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The present invention is one kind of computer executable method of tracking project progress automatically. One concept weight (W) of each task and its rate (R) are introduced for the project management, and the expression W*R expresses the ratio of the completed part to the total progress rate. The rates of all the items are summed to obtain the total project completing state. The present invention makes it possible to grasp the overall progress of project timely.

Description

technical field [0001] The present invention relates to a computer-executable method for automatically tracking project progress, in particular to a method used in the field of project management, which expresses the overall project progress through the progress R (Rate) and weight W (Wight) of each specific project Methods. Background technique [0002] In today's software project development process, the scale of the project is getting bigger and bigger, the subtasks are getting more and more, the division of labor is getting more and more detailed, and the relationship between them is becoming more and more complicated, while the market's requirements for products are becoming more and more Faster and stricter. This requires the project leader to have a very accurate grasp of the overall progress of the project in order to adjust the intensity and focus of research and development in real time to meet the needs of the market and time. [0003] However, as far as the exi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06F9/06
Inventor 刘文涵宋建福杜广海
Owner INVENTEC CORP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products