Large-span deck type cable auxiliary beam arch combined rigid frame bridge and construction method thereof
A cable-assisted girder and long-span technology, applied in arch bridges, infrastructure engineering, bridges, etc., can solve the problems of increased axial pressure and negative bending moment at the root of the main girder, small force component of the main body of the bridge, and unfavorable construction costs. , to achieve the effect of improving bearing efficiency, overcoming cracking and deflection, and high cost performance
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2022-01-04
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the field of bridge engineering, in particular to a large-span top-supported cable-assisted beam-arch composite rigid frame bridge which combines an upwardly supported arch, a continuous rigid frame bridge and a part of a cable-stayed bridge to give full play to the advantages of the combined structural system . Background technique
[0002] The top-through reinforced concrete arch bridge is a kind of thrust bridge structure system, which has been widely used due to its advantages of low cost, beautiful shape, and large spanning capacity. Large-span upward-supported reinforced concrete arch bridges are mainly suitable for mountainous areas or mountainous urban construction environments. The huge thrust generated by them requires relatively hard and complete rocks with high compressive strength as the bearing layer of the arch foot foundation. When the geological conditions of the bridge site When it is poor, it is often imposs...
Examples
Embodiment Construction
[0045] The large-span top-supported cable-assisted beam-arch composite rigid frame bridge in this embodiment includes hollow pier 3, upper chord box girder 1, lower chord box girder 2 supporting upper chord box girder 1, and hollow pier 3 and upper chord box girder 1. The upper cable tower 4 and the stay cables 8 distributed along the cable tower in the area of the beam-arch joint section 13 formed by the confluence and intersection of the upper string box girder 1 and the lower string box arch 2, the upper string box girder 1, the lower string box arch 2 and the hollow pier 3 intersect to form a beam-arch triangular area, the upper string box girder 1 is supported by hollow pier 3 and arch upper column 5 in the beam-arch triangular area, and the hollow pier 3 intersects with the arch feet of the lower string box arch 2 of the side span and mid-span , the upper column 5 of the arch is evenly distributed on the vertical surface perpendicular to the lower string box arch 2; the...