Construction method of floating floor
A construction method and ground technology, applied in the direction of floor, building, building structure, etc., can solve the problems of long-term quality control of each process, complicated construction process of floating ground, long construction time, etc., and achieve easy procurement, small Investing, high-efficiency effects
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0082] Embodiment 1, Hangzhou Radio and Television Center (Phase I) Project
[0083] Hangzhou Radio and Television Center (Phase I) project is located at Block 5, Qianjiang New City, Hangzhou, No. 68, Wujiang Road. The total construction area is 87221.4m2, with two floors underground, twenty-three floors above ground, and a building height of 99.9m (the elevation of the launch tower at the top is 183.40m). Acoustic process requirements are composed of: 1000m2 studio (four-storey height) on the first floor, 600m2 studio (four-storey height), 230m2 studio (two-storey height), 230m2 recording room (two-storey height), multi-functional hall and production, Control rooms, etc.; second-floor standard hearing room, news office, etc.; third-floor 150m2 studio (second-floor height), 100m2 studio (second-floor height), director, electric editor, news open studio (second-floor height ), news office, etc.; 100m2 studio hall (two-storey height), international conference hall (two-storey h...
Embodiment 2
[0084] Embodiment 2, Foshan City News Center, Guangdong Province
[0085] The construction of the architectural acoustic decoration project of Foshan News Center (the first bidding section) is located in Dadun, Lecong Town, Shunde District, Foshan City, with two floors underground and twelve floors above the ground. The acoustic decoration area of the first bidding section is 5300m 2 , the rooms for acoustic construction include studio, art recording room, art recording control room, live broadcast room, director room, guidance control room, multi-functional studio, quotation room, dubbing room, standard auditing room, etc. The above rooms adopt floating construction The ground construction is of good quality and meets the various acoustic indicators required by the design.
Embodiment 3
[0086] Embodiment 3, Jilin Provincial Radio and Television Center
[0087] The first phase project of Jilin Radio and Television Center is located in Jingyue Development Zone, Changchun City, with a total construction area of 85800m2 2 , including acoustic rooms: studio, live broadcast room, multi-functional hall, quotation room, art recording room, art recording control room, director's room, guidance control room, dubbing room, production room and sound gate, etc. The acoustic room adopts The construction method of floating ground. The floating floor of the acoustic room completed the construction of the acoustic room within the specified construction period with quality and quantity guaranteed, and met the requirements of various acoustic indicators, and the construction effect was good, and the use effect was good.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com