Embodiment 1
[0080] see figure 1 , 2 As shown in the schematic diagram of the step-by-step construction of the filling embankment, a step-by-step cleaning method for highway embankment construction in a preferred embodiment of the present invention is carried out according to the following steps:
[0081] (1) Before the construction of the clear list, firstly send a special person to conduct a detailed investigation of the plant resources within the land area of each construction bid section within 8, collect the rare protected plants along the line and the plants that need to be preserved and transplanted, make a book, and distribute it to the construction unit. Pay attention to protection during construction. At the same time, according to the different types of land use, classify the land along the road, and investigate the soil thickness of the topsoil in the range 8 of each type of road.
[0082] (2) The first step of surface cleaning is to clean the surface on both sides of the h...
Embodiment 2
[0103] see image 3 As shown in the schematic diagram of step-by-step cleaning of excavated roadbed, a step-by-step cleaning method for highway roadbed construction according to the preferred second embodiment of the present invention is carried out according to the following steps:
[0104] (1) For the preparation work before clearing the watch, refer to the method described in step (1) in Example 1.
[0105](2) The first step of surface cleaning construction is to clean the surface on both sides of the highway center line 1. The scope of the first step of surface cleaning reaches the width of the designed road surface width 2. At the same time, the classification of vegetation and the soil resources of the topsoil layer are carried out during the surface cleaning construction. Collect work.
[0106] (3) After the first step of surface cleaning construction is completed, determine the scope 3 of the second step of surface cleaning construction, that is, the range from the ou...
Embodiment 3
[0110] see Figure 4 As shown in the schematic diagram of the secondary surface cleaning construction of the half-filled and half-excavated roadbed, a step-by-step construction method for highway roadbed surface cleaning in the preferred third embodiment of the present invention is carried out according to the following steps:
[0111] (1) For the preparation work before clearing the watch, refer to the method described in step (1) in Example 1.
[0112] (2) The first step of surface cleaning construction is to clean the surface on both sides of the highway center line 1. The scope of the first step of surface cleaning reaches the width of the designed road surface width 2. At the same time, the classification of vegetation and the soil resources of the topsoil layer are carried out during the surface cleaning construction. Collect work.
[0113] (3) After the first step of surface cleaning is completed, the second step of surface cleaning scope 3 is determined, which is the ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com