Method for leveling two points during building construction

A building construction and horizontal technology, applied in the direction of hydrostatic pressure, can solve the problems of surveying and design method errors, large elevation point errors, large elevation errors of the bottom surface of beams and slabs, etc., and achieve the effect of strong practicability, convenient operation, and simple tools

CN102589519AInactive Publication Date: 2012-07-18JIANGSU VOCATIONAL INST OF ARCHITECTURAL TECH
4 Cites 3 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Publication Date
2012-07-18
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 1
    Figure 1
Patent Text Reader

Abstract

The invention discloses a method for leveling two points during building construction, belonging to measuring and leveling methods in construction engineering. The method is characterized by comprising the following steps of: marking a reference point on an object to be measured; carrying out water infusion into a transparent plastic hose, wherein the length of the transparent plastic hose is determined according to the distance of a measured point; and putting one horizontal plane at one end of the hose at the position of the reference point, and marking one horizontal plane at the other end of the hose, i.e. the horizontal plane at the same level as those of the measured point and the reference point. The transfer measurement on horizontal points can be carried out by using the same method. The method for leveling the two points during building construction has the beneficial effects that: the principle of a communicating vessel is utilized, the tools are simple, the operation is convenient, the practicability is strong, and the method can be operated by ordinary workers.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The present invention relates to a measuring and leveling method. Specifically, it is a method of finding the level at two points in the construction process. Background technique

[0002] Due to the strong correlation between the various buildings (structures) in the construction project and the various components of the same building (structure), the measurement and measurement work runs through the whole process, and there are various types of measurement instruments, and many measurement instruments and equipment are used. The operation is complex and requires professionally trained and qualified technicians to operate.

[0003] In the process of building construction, the workload of horizontal surveying and finding points is large and wide. The existing methods mainly include relative surveying and absolute surveying.

[0004] The so-called relative measurement and setting of the horizontal point is to select a point on the existing building as...

Examples

Embodiment 1

[0019] Example 1 Building decoration ceiling

[0020] Tools used: Clear plastic hose.

[0021] Before building and decorating the ceiling, in order to make the ceiling level, inject water into the transparent plastic hose to check the levelness of the beam plate. As shown in the attached figure, first take a point on the measuring object 1, that is, the beam or the wall, as the reference point 2, draw the reference point mark on the beam or wall with a pencil, and select a length greater than the distance from the reference point to the measured point 30 Centimeter transparent plastic hose, fill the transparent plastic hose with water, but the length of the water column is greater than the length of the reference point 2 to the measured point 3; the two ends of the transparent plastic hose 4 are bent and closed; it is operated by one person , put the horizontal plane of one end of the transparent plastic hose 4 at the position of the reference point 2, the horizontal plane of...

Embodiment 2

[0022] Example 2 Measurement and design of building five-zero line

[0023] After the construction of the building structure is completed, it is necessary to draw a horizontal line 50 cm away from the design elevation of the building ground as a reference line. Up is the five-zero line.