Electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification

A joint optimization and power system technology, applied in the direction of system integration technology, information technology support system, data processing application, etc., can solve the problems of concentrated reserve capacity, affecting the safety and reliability of the power grid, and large gaps in power generation costs

Active Publication Date: 2017-02-08
XI AN JIAOTONG UNIV +1
View PDF3 Cites 10 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, in the actual power grid, due to the uneven distribution of power generation resources and the large gap in power generation costs, the reserve capacity may be concentrated in a certain area
Considering the limit of line transmission capacity and network congestion, there may be a phenomenon that the reserve capacity cannot be called after the accident, which seriously affects the safety and reliability of power grid operation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification
  • Electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification
  • Electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0075] In order to make the object, technical solution and advantages of the present invention more clear, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the embodiments described here are only used to explain the present invention, not to limit the present invention.

[0076] In the following, the present invention will be introduced in detail by taking the combined optimal scheduling of electric energy and backup of a test grid as an example, but it should be understood that the invention is not limited thereto, and is also applicable to the combined power and backup of other grids or power operators. Optimize scheduling.

[0077] Such as figure 1 As shown, the power system electric energy-backup joint optimization dispatching method of power system considering partition backup and N-1 verification under the power market provided by the present invention includes the...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The present invention discloses an electric power system electric energy-standby optimization scheduling method considering partition standby and N-1 verification. Therefore, a combined optimization model having maximum electric energy and standby cost and considering the partition standby is established. An initial preconceive accident N-1 safety constraint is added into the optimization model, an initial scheduling scheme is obtained through solution, the transmission lines in each partition is subjected to N-1 verification, if the verification passes, the scheme is the optimization scheduling scheme of the next time, if the verification does not pass, the corresponding N-1 verification format is added into the optimization scheduling model to solve and obtain a new scheduling scheme, and the verification mentioned above is repeatedly performed until all the transmission lines pass the N-1 verification so as to obtain the final optimization scheduling scheme. The electric power system electric energy-standby optimization scheduling method considering the partition standby and the N-1 verification is helpful for ensuring the safety of the electric power and the validity of the standby so as to realize the resource optimization configuration.

Description

technical field [0001] The invention relates to a power system optimal dispatching method under the electric power market, in particular to a power system electric energy-reserve joint optimal dispatching method considering partition backup and N-1 verification under the electric power market. Background technique [0002] Power generation planning refers to planning in advance according to the load forecast, on the premise of satisfying the power balance, combined with constraints such as the upper and lower limits of the output of each unit, the maximum climbing power of each unit, and considering the actual conditions such as the start and stop of each unit and the minimum downtime. It is an important task for the dispatching department of the power system to formulate the generation power of each unit. While making a power generation plan, it is necessary to set a certain reserve capacity to deal with various uncertain factors, such as load fluctuations, forced outage of...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/04G06Q50/06
CPCG06Q10/04G06Q50/06Y02E40/70Y04S10/50
Inventor 丁涛刘凡贠靖洋别朝红陈天恩刘瑞丰
Owner XI AN JIAOTONG UNIV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products