A construction method and roadway technology, applied in tunnels, tunnel linings, installation of anchor rods, etc., can solve problems that affect construction progress and work efficiency, high labor intensity of workers, and roof caving accidents, etc., to increase compressive and flexural properties, The effect of reducing labor intensity and reducing maintenance rate

Inactive Publication Date: 2018-06-12
淮南东华欧科矿山支护设备有限责任公司
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

This support method is not only complicated in process, difficult in construction, labor-intensive for workers, waste of materials, affecting construction progress and efficiency, and high in cost, but also because there are often broken high-stress surrounding rocks and surrounding rock cracks around the roadway, gravel does not If it is solidified, it is easy to cause accidents of roof caving and then cause personal injury

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0016] The invention discloses a construction method for roadway full-anchor support, which has obvious effect in the roadway support with large section, stress concentration area, high pressure, roadway retention along the gob, and high repair rate, and can also be used for the intersection of electromechanical chambers point, permanent roadway support.

[0017] Concrete support method step of the present invention is as follows:

[0018] 1). According to the design requirements of roadway support, drill anchor holes for anchor rods or anchor cables on the broken surrounding rock around the roadway. Hollow anchor rods or anchor cables are used for anchor rods or anchor cables.

[0019] 2). Install the anchor rod or anchor cable into the anchor hole, and apply pre-tightening force to the anchor rod or anchor cable, so that the anchor rod or anchor cable is fastened in the anchor hole. After fixing the anchor rod or anchor cable to the anchor When in the hole, a metal mesh and...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a roadway full-anchor support. The construction method comprises the following steps of (1) fixing of an anchor rod, (2) whitewashing of an anchoring face, (3) maintenance of the anchoring face, (4) manufacturing of grouting slurry, (5) grouting and (6) maintenance of a roadway. Grouting reinforcement is conducted on broken surrounding rock so thatthe broken surrounding rock can form a multi-layer arch to improve the crush resistance and breaking resistance, the service life of the roadway is prolonged, the repair rate is reduced, the labor intensity is relieved, and the cost is saved.

Description

technical field [0001] The invention relates to a roadway support method, in particular to a construction method for roadway full anchor support. Background technique [0002] At present, in the support of underground roadways, the combination of anchor nets, U-shaped sheds and shotcrete is often used to support the roadways. This support method is not only complicated in process, difficult in construction, labor-intensive for workers, waste of materials, affecting construction progress and efficiency, and high in cost, but also because there are often broken high-stress surrounding rocks and surrounding rock cracks around the roadway, gravel does not If it is solidified, it is easy to cause a roof fall accident, and then cause personal injury. Contents of the invention [0003] The technical problem to be solved by the present invention is to provide a construction method for roadway full anchor support, use this method to support the roadway, solidify the broken surroun...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E21D20/00E21D20/02E21D21/00E21D11/10
CPCE21D20/003E21D11/10E21D20/02E21D21/0026
Inventor 徐永良周德军卢茂才陶友祝王涛邵山彭辉丁庆维童猛姜志明张辉蔡乐乐
Owner 淮南东华欧科矿山支护设备有限责任公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products