Construction method of an underground superimposed double-pipe common well structure
A construction method and technology of well structure, which are applied in basic structure engineering, excavation, marine engineering and other directions, can solve the problems of large enclosed area, large land occupation, and large impact on residents' lives, so as to reduce drainage pressure, save construction time, The effect of preventing sinking
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment a
[0075] refer to figure 1 and figure 2 , which is embodiment a of the present invention, specifically:
[0076] A construction method for an underground superimposed double-pipe common well structure, comprising the following steps:
[0077] Step A) Drilling several annular waterproof holes, pouring concrete in the waterproof holes to form a concrete waterproof column 4, thereby forming a waterproof cylinder;
[0078] Step B) Excavating the excavation well 1 in the waterproof cylinder;
[0079] Excavation well 1 is made like this:
[0080] Step b1) Excavating a pit in the waterproof cylinder;
[0081] Step b2) setting steel bars in the pit and placing a ring-shaped formwork, the steel bars are arranged between the formwork and the vertical wall of the pit, and concrete is poured between the formwork and the vertical wall of the pit, thereby forming a reinforced ring 2 made of concrete;
[0082] Step b3) Excavating at the bottom of the pit;
[0083] Step b4) setting steel...
Embodiment b
[0120] refer to image 3 , which is embodiment b of the present invention, specifically:
[0121] The connection section of the present embodiment is a ditch 311 with an upward opening, and a support frame is provided in the excavation well 1. The right vertical plate 42 on the right side, the upper end of the left vertical plate 41 is provided with the cross strut plate 43 that horizontally arranges, and the upper connection pipe 31 is located on the cross strut plate 43, is provided between the cross strut plate 43 and the ditch 311 The sealing plate 45 that is set horizontally, is provided with cover 44 on the cover plate 45, and cover 44, cover plate 45 are synthesized into block assembly, and the left side of block assembly is connected with left vertical plate 41, and the right side of block assembly is connected with The right vertical plate 42 is connected so that the water-passing ditch 311 is sealed in the water-passing space, and the water-passing space is composed...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com