The present application relates to the technical field of bridge demolition, in particular to a kind of multi-span
solid-web
masonry arch bridge quick demolition method, comprising the following steps: based on the
data information of the multi-span
arch bridge to be demolished, the three-dimensional model of the multi-span
arch bridge is established, the vertical
counterforce and
horizontal force suffered by the arch foot of the
arch bridge are calculated based on the three-dimensional model of the multi-span arch bridge, the best fixing position of the steel
wire rope for demolition of arch bridge on the
pier is calculated, and the specification of the required steel
wire rope is calculated according to the best fixing position, the steel
wire rope for pulling is installed at the best fixing position, the arch filler in the multi-span arch bridge is excavated, and the arch rib of the side span is chiseled from outside to inside until the whole side span collapses and falls into the river, the earthwork falling into the river is leveled as a construction access, the possible collapse range of the arch bridge is calculated, the pre-set steel wire
rope is pulled outside the possible collapse range of the arch bridge until the arch
bridge collapses.