The invention discloses a construction method for quickly breaking and dismantling a 
masonry arch bridge based on 
bridge deck cutting, which comprises the following steps of: 1, collecting or actually measuring structural parameters of the 
masonry arch bridge to be broken and dismantled, and acquiring span, rise, 
bridge deck pavement thickness, width and 
steel bar arrangement condition; step 2, 
cutting the to-be-broken 
masonry arch bridge deck, wherein the 
cutting position at least comprises bridge 
deck pavement right above an arch foot on one side; thirdly, a long-arm hook 
machine is adopted for breaking and dismantling an arch foot on the other side of the masonry 
arch bridge, and the whole span of the masonry 
arch bridge collapses and falls off; and fourthly, the collapsed and fallen masonry materials are cleared and transported, and masonry 
arch bridge forcible entry operation is completed. According to the method, the whole-span collapse can be realized, the masonry material is crushed into small blocks by utilizing the falling energy of the whole-span collapse, the quick breaking and removing and clearing are realized, the breaking and removing 
safety risk is reduced, the construction period is shortened to the greatest extent, the construction cost is reduced, and the interference and influence on the surrounding environment are reduced.