Construction method for cantilever assembly steel arches for cast-in-situ large-span concrete arch bridge
A construction method and technology for steel arches, which are applied in the field of cantilevered steel arches for arch bridges, can solve problems such as being difficult to implement and cumbersome, and achieve the effects of reasonable structure, advanced technology, and reliable fixing.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2015-01-07
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to the technique of suspended steel arch frames for arch bridges, which is a construction method for the suspended steel arch frames of cast-in-situ large-span concrete arch bridges. Background technique
[0002] There are many methods for splicing steel arch frames of existing arch bridges, such as the assembly method of universal rods, but the construction period of universal rod assembly is very long, and the construction process has a great impact on the environment, and it will be affected by environmental factors such as flood seasons. thus affecting the construction.
[0003] In the cantilevered steel arch frame, the method of joint connection and pin connection of male and female joints is often used. Although this method is firmly connected, it is too rigid and cannot realize splicing and span adjustment.
[0004] At the same time, the method of realizing the lateral sliding of the steel arch frame by using a traversing ...
Examples
Embodiment 1
[0039] Construction method of cantilevered steel arch frame of cast-in-place long-span concrete arch bridge. The steel arch frame is composed of standard segment 2, adjustment segment 4, vault segment 3 and arch foot segment 1. The construction process mainly includes the steel arch Frame assembly and steel arch lateral movement are carried out simultaneously on both sides of the bridge span during construction. Its characteristics are: in the process of segmental connection, the horizontal system adopts the horizontal connection method, and the top surface of the arch frame and the ground adopt the flat connection method; The connection between the sections is connected by the lower chord pin shaft and the upper chord bolt connection; the specific construction is carried out according to the following steps:
[0040] Step 1, set the steel arch abutment; the steel arch abutment is a temporary abutment used to support the cast-in-place construction load. At the same time as the...
Embodiment 2
[0050] Taking the Fuxi River Bridge as an example, the Fuxi River Bridge is located on the eastern edge of the Guizhou Plateau. The bridge area is a plateau structure erosion-denudation low-middle mountain valley landform. The altitude near the bridge area is between 324.5 and 364m, with a relative height difference of 39m. The covering layer of the bridge area is cultivated soil, silty clay and alluvial-diluvial pebble soil. The upper structure of Fuxi River Bridge adopts 5×20m (prestressed concrete hollow slab) + 120m (reinforced concrete box arch) +2 ×20m (prestressed concrete hollow slab). The main hole of the lower structure adopts cast-in-place reinforced concrete abutment and cast-in-place concrete foundation, and reinforced concrete bent piers are set on the arch, and the junction piers No. The pile foundation and abutment foundation are cut and expanded foundations, and the abutments on both banks are gravity U-shaped abutments.
[0051]The steel arch is composed of ...