Sectionalized construction method of deep and large foundation pit
A construction method and foundation pit technology, which is applied in infrastructure engineering, excavation, construction, etc., can solve the problems of excessive influence on the surrounding environment, irregular plane shape, large excavation area of foundation pit, etc., and achieve convenient construction and safety High, reduce the effect of space-time effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0032] Example 1: Combining figure 1 Illustrate the divisional construction method of the deep and large foundation pit of the present invention, this project plans to build a large-scale shopping center with seven floors above the ground and three floors underground. Triangular (with short side a, long side b, and hypotenuse c), since the excavation area of the foundation pit is too large, if it is divided into east-west or north-south areas for construction according to the conventional method of pit division, although the The excavation area of the deep and large foundation pit ensures the safety of the foundation pit project, but it is not conducive to the construction of the main structure and prolongs the construction period of the main structure. Adopt the partition construction method of the present embodiment, the steps are as follows:
[0033] One, according to the engineering geological conditions of the said deep and large foundation pit 100 construction site,...
Embodiment 2
[0043] Embodiment 2: Combination figure 2 Explain the divisional construction method of the deep and large foundation pit of the present invention. This project plans to build a dance center. The project foundation pit covers an area of 80,000 m2, and the excavation depth is 6.8m to 11.0m. The plane shape is long and the maximum span is more than 300 meters. , surrounded by 6 historically protected buildings (attached figure 2 B1-B6 in the middle), the distance from the excavation sideline of the foundation pit is the closest to only 3.7m. If the foundation pit is divided into two parts for sub-pit construction according to the conventional method of sub-pit, although this reduces the excavation area of the foundation pit and increases the safety of the foundation pit, it cannot control the excavation of the foundation pit to the greatest extent. The impact of excavation on surrounding historic buildings. Adopt the partition construction method of the present embodimen...
PUM
Property | Measurement | Unit |
---|---|---|
Width | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com