Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Simultaneous Construction Method of Adjacent Foundation Pit with Unequal Height

A construction method and synchronous construction technology, applied in infrastructure engineering, excavation, construction, etc., can solve problems such as waste of steel bars, concrete, poor connection conditions of steel bars, and inability to synchronize excavation, etc., to reduce the amount of work, ensure integrity, Avoid the effect of cross-jobs

Active Publication Date: 2019-06-21
ERCHU CO LTD OF CHINA RAILWAY TUNNEL GRP
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0008] 1. The parts below the ramp (shallow pit) and the main line (deep pit) steel support cannot be excavated synchronously, resulting in the base excavation of the construction ramp, which needs to be carried out after the main line structure is completed, and the construction period is long
[0009] 2. During the construction of the ramp structure, the ground connection wall needs to be removed, causing large disturbance and wasting resources such as steel bars and concrete
[0010] 3. The connection conditions between the side wall of the main line and the bottom plate of the ramp are poor, and the workload of planting reinforcement is large, or a mechanical connection sleeve is reserved, which is easy to misalign and leak

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Simultaneous Construction Method of Adjacent Foundation Pit with Unequal Height
  • Simultaneous Construction Method of Adjacent Foundation Pit with Unequal Height
  • Simultaneous Construction Method of Adjacent Foundation Pit with Unequal Height

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0058] The technical solution of the construction method of the present invention will be clearly and completely described below in conjunction with the accompanying drawings of the description.

[0059] The construction method of the present invention includes figure 1 The construction of the initial section shown with the figure 2 The terminal section shown is constructed in two phases.

[0060] Step 1, construction steps of a typical section in the initial section:

[0061] Step 1, adjust the height of the ground connection wall and the position of the steel support:

[0062] (11) adjust the height of ground connection wall 5, the height of ground connection wall 5 is below the bottom plate 40 of 2 of the first deep foundation pit 1 and the second deep foundation pit all the time;

[0063] (12) Adjust the position of the steel support. When the height difference between the first deep foundation pit 1, the second deep foundation pit 2, the third shallow foundation pit 3...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a synchronous construction method of near height-unequal foundation pit. The construction method comprises the main steps of: adjusting the height of a ground continuous wall and the position of a steel support; constructing the ground continuous wall; constructing a SMW construction pile; constructing a SMW construction pile crown beam and a concrete support; excavating deep foundation pit and shallow foundation pit earth to the bottom of the steel support; erecting the steel support; excavating the deep foundation pit and shallow foundation pit earth; constructing a baseplate of a deep foundation pit structure; dismounting the steel support; constructing a side wall of the deep foundation pit structure; synchronously constructing a top plate of the deep foundation pit structure and a baseplate of a shallow foundation pit structure; constructing a side wall of the shallow foundation pit structure; filling the earth at the upper part of the top plate of the deep foundation pit; dismounting the concrete support; and the like. The construction method has the following beneficial effects: the top surface elevation of the ground continuous wall of the deep foundation pit is parallel to the bottom of the shallow foundation pit, so that the height of the ground continuous wall is reduced, and the engineering quantity of an envelop structure is reduced; and the earth excavation of the deep foundation pit and the shallow foundation pit and the construction of a main body structure are convenient, so that repeated procedure conversion is reduced, the cross operation is prevented, and the efficiency is improved.

Description

technical field [0001] The invention relates to the technical field of foundation pit construction, in particular to a method for synchronously constructing foundation pits adjacent to unequal heights. Background technique [0002] Open-cut foundation pit construction technology has a long history, but the second-line and third-line parallel adjacent foundation pits of different heights are relatively rare in open-cut foundation pit engineering. How to do a good job in the connection between the earthwork excavation of this type of foundation pit and the construction of the main structure, to ensure the quality of foundation pit construction, construction safety, construction progress, and reduce engineering costs is a subject worth exploring. [0003] Adjacent foundation pits with unequal heights are easy to be encountered in municipal road projects and cross-river (river) tunnel projects. In order to increase the benefit range of traffic along both sides of the river (riv...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D17/02E02D17/04
CPCE02D17/02E02D17/04
Inventor 刘国秀王厚涛赵宝锋张振亚蒋树锋闫丁灿张柯程斌安斌曹露平张小莉张君王政
Owner ERCHU CO LTD OF CHINA RAILWAY TUNNEL GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products