Outer drainage system of inverted arch body of tunnel rich water formation and construction method

A technology of water-rich strata and drainage system, which is applied in the directions of drainage, earthwork drilling, safety devices, etc., can solve the problems such as the inability to closely adhere the primary support of the secondary lining of the inverted arch, affecting the safety quality in the operation stage, and affecting the economic benefits of operation. , to achieve the effect of reducing construction renovation costs, enriching construction methods, and ensuring operational quality and safety.

CN109236366AInactive Publication Date: 2019-01-18ERCHU CO LTD OF CHINA RAILWAY TUNNEL GRP
8 Cites 2 Cited by

Patent Information

Authority / Receiving Office
CN · China
Current Assignee / Owner
Publication Date
2019-01-18
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses an outer drainage system of an inverted arch body of a tunnel rich water formation and a construction method. The system is arranged between an initial support of the invert arch and a second lining of the invert arch, and comprises 1-3 double-wall perforated bellows disposed at the bottom of the invert arch. The double-walled perforated bellows are longitudinally disposed,the openings of each of the double-walled perforated bellows serve as water inlets for accumulated water on the bottom of the invert arch, and each of the double-walled perforated bellows is communicated with tunnel ditches for discharging the accumulated water in a pipe into the tunnel ditches; when the number of the double-wall perforated bellows is greater than one, the plurality of the double-walled perforated bellows are arranged side by side and communicated with each other. The method is fast, convenient and easy to operate, forms a complete drainage system between the initial supportof the invert arch and the second lining of the invert arch, largely solves the problem that the accumulated water at the bottom of the tunnel cannot be discharged, prevents the water at the bottom ofthe inverted arch from gathering, and creates a pumping effect that ensures operational quality and safety.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention belongs to the technical field of tunnel engineering construction, and in particular relates to an external drainage system and a construction method of an inverted vault in a water-rich stratum of a tunnel. Background technique

[0002] In the construction of tunnels in water-rich strata in China, there was no specific construction method to deal with the accumulated water at the bottom of the inverted arch of the tunnel in the past. Only relying on management requirements and the responsibility of the construction personnel on site, the water should be drained as much as possible before pouring concrete. As a result, the second lining of the inverted arch cannot be closely attached to the primary branch of the inverted arch during pouring. After the construction of the inverted arch is completed, water is likely to form between the primary branch of the inverted arch and the second lining of the inverted arch, and the water at the bottom...

Examples

Embodiment Construction

[0023] The present invention is an external drainage system of an inverted vault in a water-rich strata of a tunnel, such as figure 1 As shown, it is arranged between the primary branch of the inverted arch and the second lining of the inverted arch, including 1 to 3 double-walled perforated corrugated pipes 1 arranged at the bottom of the inverted arch. The opening of the double-walled perforated bellows 1 is used as the water inlet of the accumulated water at the bottom of the inverted arch, and each of the double-walled perforated bellows 1 is connected with the tunnel ditch, and is used to drain the accumulated water entering the pipe into the tunnel water. In the ditch; when the number of double-wall perforated corrugated pipes 1 is greater than one, multiple double-wall perforated corrugated pipes 1 are arranged side by side and communicate with each other. The double-wall perforated corrugated pipe 1 communicates with the tunnel ditch in multiple places, and is arranged...