Construction method for concrete foundation of in-station equipment foundation
What is Al technical title?
Al technical title is built by PatSnap Al team. It summarizes the technical point description of the patent document.
A technology of concrete foundation and station equipment, applied in the direction of basic structure engineering, construction, etc., can solve the problems of prolonging construction time, uncontrollable overall quality, and unreasonable arrangement of overall engineering, etc., to achieve the effect of ensuring construction time and construction quality
Pending Publication Date: 2022-03-22
BEIJING URBAN CONSTR GROUP
View PDF4 Cites 0 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
[0005] The purpose of the present invention is to provide a concrete foundation construction method for the equipment foundation in the station, so as to solve the problems that the overall project cannot be reasonably arranged in the above-mentioned background technology, the overall quality is uncontrollable, and the construction time is prolonged.
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment Construction
[0028] see figure 1 , the embodiment of the present invention provides a construction method for concrete foundation of equipment foundation in a station, comprising the following steps,
[0029] 1. Positioning and setting out measurement:
[0030] 1.1 Construction measurement preparation
[0031] Construction survey preparation is an important link to ensure the smooth progress of the whole process of construction survey, including the review of drawings, the handover and verification of measurement positioning reference points, and the verification and verification of measuring instruments.
[0032] 1.1.1. Fully understand the design intent, carefully familiarize yourself with and review the drawings.
[0033] 1.1.2. Conscientiously do a good job in the handover of measurement results and on-site points or piles, and properly protect the points or piles.
[0034] Selection of measuring instruments. The terrain of the cableway line is relatively complex, and the height di...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
PUM
Login to view more
Abstract
The invention relates to the field of concrete construction, and discloses an in-station equipment foundation concrete foundation construction method which comprises the following steps: S1, positioning and setting-out measurement: measuring and positioning a construction site by adopting a total station, a theodolite, a level gauge, a box staff and a steel ruler, and carrying out plane axis positioning measurement setting-out and elevation control; s2, foundation excavation and transportation are conducted, specifically, earth and stone excavation generally follows the procedure from top to bottom, earthwork is conducted firstly and then stone excavation is conducted, groove cleaning is conducted after foundation excavation is completed, and foundation groove inspection needs to be conducted after excavation is completed; s3, reinforcing steel bar engineering is conducted, specifically, reinforcing steel bar connection is conducted firstly, the reinforcing steel bar connection mode is the combination of mechanical connection and binding lap joint, and quality inspection is conducted after reinforcing steel bar connection is completed; through cooperation of foundation excavation and transportation, bolt installation engineering, formwork engineering, concrete engineering and the like, excavation of the cableway foundation and cable erection can be conducted at the same time, limited construction time is fully utilized, and the overall construction time is guaranteed.
Description
technical field [0001] The invention relates to the technical field of concrete construction, in particular to a concrete foundation construction method for equipment foundations in a station. Background technique [0002] Concrete construction is to make and bind steel bars, place and fix formwork, use raw materials that meet quality requirements, mix, transport, pour, and maintain according to the specified ratio according to the requirements of the design drawings, and at the same time carry out the whole process of each link Quality control and inspection. [0003] The construction of the cableway foundation has to go through winter construction, and the construction period is short. To complete the construction of the project, the reasonable interspersion of the overall project is particularly important. The concrete foundation construction method of some in-station equipment foundations in the prior art cannot reasonably arrange the overall project, which makes the ov...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.