Ballasting method in large-span girder cantilever construction
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
- Publication Date
- 2014-01-15
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to a bridge construction method, in particular to a weight method in the cantilever construction of a large-span steel girder. Background technique
[0002] During the steel beam construction process, the side spans are generally erected with temporary support piers to assist the cantilever erection. After the side span steel beam cantilever is erected to the main pier, the full cantilever erection is carried out. Finally, the middle span is closed by jacking down and longitudinally moving the steel beam. When the cantilever length of the steel girder is large, it is necessary to press on the side span to meet the requirement of anti-overturning stability safety factor K≧1.3.
[0003] There are two traditional weighting methods:
[0004] (1) Physical weight. Water tanks or concrete, steel and other objects are used for ballasting on the bridge deck or on the top chord of the steel girder. The advantage of this method is that the...