Project progress management method based on critical chain

A management method and project schedule technology, applied in the field of project schedule management, can solve problems such as complex logical relations and achieve artistic effects

Inactive Publication Date: 2014-04-30
BEIJING SIMULATION CENT
View PDF0 Cites 37 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0010] (4) The critical path has a strict front-to-back relationship, whil

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Project progress management method based on critical chain
  • Project progress management method based on critical chain
  • Project progress management method based on critical chain

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0023] Such as figure 1 Shown is the implementation process of the project schedule management of the present invention, the implementation process of the project schedule management based on the critical chain is completed by five modules, the initialization module, plan formulation, plan execution, plan tracking and statistics module. The initialization module is responsible for functions such as project startup and project size estimation. The planning module is mainly responsible for the functions of stage definition, task creation, personnel creation, resource input and allocation, etc. The plan execution module is mainly responsible for key chain identification, buffer insertion, plan update and other functions. The plan tracking module is mainly responsible for the monitoring of the project operation process, risk identification and other functions. The statistics module is mainly responsible for the statistics of resource usage information and workload information. ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a project progress management method based on a critical chain. The project progress management method based on the critical chain comprises the following steps that (1) an initialization module is started and a basic framework of project management is generated; (2) a plan making module creates webs, makes a network planning chart and establishes a personnel and resource table; (3) a plan implementation module conducts an estimation on a time limit of a project according to the mean square error method, project buffer time and feeding buffer time are worked out, an MRCPSP module is established, and a final progress planning table constrained by a project logical relationship and resources is determined; (4) a plan tracking module monitors the implementation condition of the project and recognizes a project progress risk; (5) a project statistic module conducts statistics on the project workload and the resource use condition. By the adoption of the project progress management method based on the critical chain, dynamic management of the project implementation progress and the continuous improvement on the whole project management process are achieved on the premise that constraint conditions of the implementation time of jobs and the precedence relationship between the jobs are met and the resource constrain conditions are met.

Description

technical field [0001] The invention relates to a project progress management method, in particular to a critical chain-based project progress management method. Background technique [0002] Project schedule management refers to the management of the progress of each stage and the deadline for the final completion of the project during the project implementation process. It is to draw up a reasonable and economical progress plan (including sub-plans of multi-level management) within the specified time. During the process of implementing the plan, it is often necessary to check whether the actual progress is carried out according to the plan. Find out the reason in time, take necessary remedial measures or adjust and modify the original plan until the project is completed. Its purpose is to ensure that the project can achieve its overall goals under the premise of meeting its time constraints. Project schedule management methods mainly include: [0003] (1) Gantt chart, m...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): G06Q10/06
Inventor 周军华
Owner BEIJING SIMULATION CENT
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products