A construction control method for corridors composed of long-span trusses with different lengths
Patent Information
- Authority / Receiving Office
- CN Β· China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- SHANGHAI MECHANIZED CONSTR GRP
- Publication Date
- 2017-11-24
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the field of building construction, and in particular to a method for controlling the construction of a corridor composed of long-span trusses with different lengths. Background technique
[0002] Corridor structures are mostly used in large-scale commercial plazas to connect various main structures, and most of them are steel truss structures. At present, temporary support and scattered hoisting construction techniques are mostly used, but the conventional hoisting and unloading techniques are implemented with different lengths. For large-span trusses, during the unloading process, there will be differences in settlement due to the different deflections of the two trusses, which will affect the level of the floor structure beams and have a greater impact on subsequent construction, and the construction will be carried out directly according to the drawing if one end is rigidly connected and the other end is hinged It will also...