Deep underwater transportation corridor structures and construction method thereof
A construction method and corridor technology, applied to underwater structures, infrastructure engineering, water conservancy projects, etc., can solve the problems of no underwater building protection structure construction methods, etc., to reduce the number of construction joints, compensate for shrinkage, and improve resistance The effect of permeability
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2017-05-17
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the technical field of underwater building structures, in particular to a deep underwater traffic corridor structure, and also relates to a construction method of the structure. Background technique
[0002] After the Three Gorges Project was impounded, the Baiheliang inscriptions in Fuling, Chongqing were submerged under 10-40m of water for many years. In February 2001, it was determined to adopt the in-situ underwater protection plan for the Baiheliang inscriptions, that is, to build a protective cover on the inscriptions to isolate the cultural relics inscriptions from the external environment, thereby achieving the purpose of protection. The Baiheliang protection project consists of three parts: the ground exhibition hall, the underwater protection body and the traffic corridor. Traffic corridors are divided into slope-shaped traffic corridors and horizontal traffic corridors. The slope-shaped traffic corridors are basica...
Examples
Embodiment Construction
[0031] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0032] Such as figure 1 As shown, the deep underwater traffic corridor structure includes a horizontal traffic corridor structure 1 and a slope-shaped traffic corridor structure 2; the horizontal traffic corridor structure 1 is basically arranged on the riverbed 6, and one end is connected to the slope-shaped traffic corridor structure The other end is connected to the underwater protection body 5; the slope-shaped traffic corridor structure 2 is basically arranged on the slope of the embankment 3, the slope is 30°, supported by the pile foundation 7, and one end is connected to the horizontal traffic corridor structure 1 is connected, and the other end is connected with the ground hall 4.
[0033] Such as figure 2As shown, the front section of the main structure of the horizontal traffic corridor structure 1 and the slope-shaped traffic cor...