Construction progress prediction method and system based on BIM model
A construction progress and model technology, applied in the field of substation construction management informatization, can solve problems such as prolonging the construction period, occupying time, unfavorable construction progress on time, etc., and achieve the effect of increasing reliability assurance, reducing complexity and increasing convenience
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0058] Combining the above-mentioned inventive idea of the technical solution of the present invention, a method for predicting the construction progress based on the BIM model, such as figure 1 shown, including:
[0059] Step S100: Obtain construction information to build a three-level model, which includes a macro model of the overall project, a meso model of ancillary buildings, and a micro model of equipment lines.
[0060] According to the content of the substation project, all the construction information related to the project is obtained, and these information are imported into the BIM system to establish the project model. The information is divided into first to third model data according to the level of refinement of the information content. The first model data includes the 3D model of the substation project, the overall construction progress and engineering information. In this modeling, different materials and colors are used to represent each area, walls, roa...
Embodiment 2
[0083] Combining the above-mentioned inventive idea of the technical solution of the present invention, a system for predicting the construction progress based on the BIM model, such as Image 6 shown, including:
[0084] The acquiring unit 100 is configured to acquire construction information.
[0085] The construction unit 200 is configured to construct and save a three-level model according to the construction information. The three-level model includes a macro model of the overall project, a meso model of ancillary buildings, and a micro model of equipment lines.
[0086] The preparation unit 300 is used to prepare the construction progress plan. Such as Figure 7 As shown, the compilation unit 300 includes a creation subunit 301 , a corresponding subunit 302 and a formulation subunit 303 .
[0087] The creating subunit 301 is used to obtain schedule task arrangement and create engineering task.
[0088] The corresponding subunit 302 is used for corresponding the sch...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com