Project cost progress management control system and method based on big data

A technology for project cost and progress management, applied in data processing applications, commerce, instruments, etc., can solve the problems of time-consuming project cost evaluation, prone to calculation errors, and low calculation efficiency, so as to save time and accuracy of project cost evaluation High, computationally efficient effects

Inactive Publication Date: 2020-07-14
QINGDAO BINHAI UNIV
View PDF0 Cites 10 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] To sum up, the problems existing in the existing technology are: the existing project cost progress management control system and method based on big data usually calculate the project cost by the cost personnel according to the engineering design data, the calculation efficiency is low, and calculation errors are prone to occur ; At the same time, the evaluation of project cost is time-consuming and has poor accuracy

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Project cost progress management control system and method based on big data
  • Project cost progress management control system and method based on big data
  • Project cost progress management control system and method based on big data

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0085] The big data-based project cost schedule management and control method provided by the embodiment of the present invention is as follows: figure 1 As shown, as a preferred embodiment, such as image 3 As shown, the method for calculating the project cost through the cost calculation program combined with the budget data provided by the embodiment of the present invention includes:

[0086] S201. Obtain engineering raw data through engineering equipment.

[0087] S202. Extract project cost budget information matching the project original data from a preset project cost database.

[0088] S203. Calculate a project cost budget result according to the project cost budget information and the project raw data;

[0089] S204. Generate a project cost proposal according to the project original data and the project cost budget result.

[0090] The original engineering data provided by the embodiment of the present invention includes basic engineering information, basic technic...

Embodiment 2

[0106] The big data-based project cost schedule management and control method provided by the embodiment of the present invention is as follows: figure 1 as shown in Figure 4 As shown, as a preferred embodiment, the method for analyzing the project cost through the cost analysis program provided by the embodiment of the present invention includes:

[0107] S301, making an Excel report of project cost, and completing the entry of actual cost attributes.

[0108] Wherein, the report includes multiple engineering categories, each engineering category has multiple equipment categories, each equipment category has multiple attributes, and the attributes include actual cost attributes and automatic analysis attributes;

[0109]S302. Through the project cost analysis program, query the standard cost data corresponding to each equipment category under the current project category in turn, and calculate the relative deviation value.

[0110] S303, judging the range of the relative d...

Embodiment 3

[0113] The big data-based project cost schedule management and control method provided by the embodiment of the present invention is as follows: figure 1 as shown in Figure 5 As shown, as a preferred embodiment, the method for evaluating the project cost through the cost evaluation program provided by the embodiment of the present invention includes:

[0114] S401, establishing a construction project cost evaluation index table with dimensions, types, and hierarchical relationships through the evaluation program.

[0115] S402, performing automated cost evaluation analysis on the development projects participating in the evaluation through the construction project cost evaluation index table.

[0116] S403. Automatically generate a list of doubtful points in cost evaluation corresponding to the development project according to the evaluation and analysis results.

[0117] In step S401 provided by the embodiment of the present invention, the dimensions include year and regio...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention belongs to the technical field of project cost progress management control. The invention discloses a project cost progress management control system and method based on big data. The project cost progress management control system based on big data comprises a project data acquisition module, a main control module, a cost budget module, a cost calculation module, an accounting module, a cost analysis module, a cost evaluation module, a data storage module and a display module. The engineering cost is automatically calculated through the cost calculation module, the accuracy is high, and the calculation efficiency is high; the construction cost evaluation module is automatically applied to the real estate development project participating in engineering construction cost evaluation, whether the enterprise self-reported engineering construction cost of the specific real estate development project corresponding to different dimensions exceeds the standard or not is automatically presented, and the engineering construction cost evaluation time for the specific real estate development project is greatly saved; and a project cost auditing basis is provided accurately and efficiently.

Description

technical field [0001] The invention belongs to the technical field of project cost schedule management and control, and in particular relates to a big data-based project cost schedule management control system and method. Background technique [0002] Project cost refers to the total cost of a certain project construction, that is, the sum of one-time expenses for the planned reproduction of fixed assets, the formation of corresponding intangible assets and the establishment of working capital for the project. Obviously, this meaning is defined from the perspective of investors-owners. After investors select a project, they must make decisions through project evaluation, and then carry out a series of investment management activities such as design bidding, engineering bidding, and completion acceptance. All expenses paid in investment activities form fixed assets and intangible assets. All these expenses constitute the project cost. In this sense, the project cost is th...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/06G06Q10/10G06Q30/06G06Q30/08G06Q50/08
CPCG06Q10/06393G06Q10/103G06Q30/0611G06Q30/08G06Q50/08
Inventor 侯蕾
Owner QINGDAO BINHAI UNIV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products