Method and system for predicting post-earthquake restoration process of community building group
A prediction method and technology of building groups, applied in the direction of prediction, complex mathematical operations, data processing applications, etc., can solve the problems of lack of prediction schemes for the post-earthquake repair process of community building groups, and achieve the effect of reducing redundancy and waste
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
no. 1 example
[0078] This embodiment provides a method for predicting the post-earthquake repair process of community building groups, which can be implemented by electronic equipment. It first performs data preparation, including the preparation of the post-earthquake damage status of community building groups and other related data; Function classification determines its priority in restoration; then establishes a single building restoration model to simulate the restoration process of a single building structure under certain resource conditions; finally, establishes a community building group restoration process resource allocation model to realize community building restoration under different resources. Group repair process prediction.
[0079] Specifically, the execution flow of the method is as follows figure 1 shown, including the following steps:
[0080] S1. Obtain the post-earthquake damage status, building function and building area of community buildings;
[0081] Through ...
no. 2 example
[0149] This embodiment provides a system for predicting the post-earthquake repair process of community buildings, including the following modules:
[0150] The data preparation module is used to obtain the post-earthquake damage status, building function and building area of community buildings;
[0151] A building restoration priority determination module, configured to determine the priority of each building during restoration through the classification of building functions;
[0152] The post-earthquake repair model building module of a single building is used to use the post-earthquake damage state and building area of the community building group to calculate the engineering quantity required for repairing the building, establish a single building repair model, and simulate a single building under certain resource conditions Structural repair process;
[0153] The resource allocation model of the community building group repair process and the community building gro...
no. 3 example
[0156] This embodiment provides an electronic device, which includes a processor and a memory; at least one instruction is stored in the memory, and the instruction is loaded and executed by the processor, so as to implement the method of the first embodiment.
[0157] The electronic device may have relatively large differences due to different configurations or performances, and may include one or more processors (central processing units, CPU) and one or more memories, wherein at least one instruction is stored in the memory, so The above instruction is loaded by the processor and executes the above method.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com