Construction layout for underground caverns in nuclear island powerhouse of underground nuclear power plant

a construction layout and nuclear power plant technology, applied in nuclear engineering, greenhouse gas reduction, nuclear elements, etc., can solve the problems of adversely affecting the construction of adits, heavy excavation of terrain posing hidden risks, and lack of construction layout, etc., to achieve convenient construction, short construction time, and high modularity.

Active Publication Date: 2019-06-11
CHANGJIANG SURVEY PLANNING DESIGN & RES
View PDF18 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Benefits of technology

The modularized layout reduces construction time and costs, enhances safety, and allows for efficient construction by minimizing the number of construction channels and ensuring stability, making the process more economical and convenient.

Problems solved by technology

Conventional construction layouts for caverns of an underground nuclear power plant leave much to be desired.
In general, the distribution of the caverns is irregular, which means that parts of the terrain are heavily excavated posing hidden risks.
In addition, the random distribution of the primary caverns adversely affects the construction of adits.
This delays the construction time and increases the investment cost.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction layout for underground caverns in nuclear island powerhouse of underground nuclear power plant
  • Construction layout for underground caverns in nuclear island powerhouse of underground nuclear power plant
  • Construction layout for underground caverns in nuclear island powerhouse of underground nuclear power plant

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0020]For further illustrating the invention, experiments detailing a construction layout for underground caverns in a nuclear island powerhouse of an underground nuclear power plant are described below. It should be noted that the following examples are intended to describe and not to limit the invention.

[0021]As shown in FIGS. 1-3, a construction layout for underground caverns in a nuclear island powerhouse of an underground nuclear power plant comprises: two primary caverns accomodating nuclear reactor powerhouses 1, combined caverns, electric powerhouse caverns 2, pressure relief caverns 7, a first primary traffic tunnel 8, a second primary traffic tunnel 9, a third primary traffic tunnel 10, a top adit system, a ground adit system, a primary steam channel 11, a device conveying channel 12, secondary traffic tunnels 13, and a side traffic tunnel 14.

[0022]Two primary caverns accomodating nuclear reactor powerhouses 1 are provided. A connecting line of medial axes of the two prima...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A construction layout for underground caverns in a nuclear island powerhouse of an underground nuclear power plant, including: two primary caverns accomodating nuclear reactor powerhouses, combined caverns, electric powerhouse caverns, pressure relief caverns, a first primary traffic tunnel, a second primary traffic tunnel, a third primary traffic tunnel, a top adit system, a ground adit system, secondary traffic tunnels, and a side traffic tunnel. Each combined cavern and each electric powerhouse cavern are disposed at two sides of each primary cavern, respectively. Two combined caverns are in end-to-end connection and the arrangement direction of the two combined caverns are in parallel to the connecting line of the medial axes of the two primary caverns. Each pressure relief cavern is disposed between each combined cavern and a corresponding electric powerhouse cavern.

Description

CROSS-REFERENCE TO RELATED APPLICATIONS[0001]This application is a continuation-in-part of International Patent Application No. PCT / CN2015 / 079879 with an international filing date of May 27, 2015, designating the United States, and further claims foreign priority benefits to Chinese Patent Application No. 201410264520.3 filed Jun. 13, 2014, and to Chinese Patent Application No. 201420316976.5 filed Jun. 13, 2014. The contents of all of the aforementioned applications, including any intervening amendments thereto, are incorporated herein by reference. Inquiries from the public to applicants or assignees concerning this document or the related applications should be directed to: Matthias Scholl P.C., Attn.: Dr. Matthias Scholl Esq., 245 First Street, 18th Floor, Cambridge, Mass. 02142.BACKGROUND OF THE INVENTIONField of the Invention[0002]The invention relates to a construction layout for underground caverns in a nuclear island powerhouse of an underground nuclear power plant.Descript...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(United States)
IPC IPC(8): G21D1/00E21D9/14G21D1/02E02D29/00E21D13/00G21C1/00
CPCE21D9/14G21D1/00E02D29/04E21D13/00Y02E30/40G21C1/00Y02E30/00Y02E30/30
Inventor YANG, QIGUINIU, XINQIANGLIU, LIXINLIU, BAIXINGZHAO, XINSU, LIJUNLI, FENGYANG, XUEHONGZHANG, ZHIJUNMIU, ZHENGJIANZHANG, ZHIGUOLIU, HAIBOTAO, TIELINGWAN, YANLEI
Owner CHANGJIANG SURVEY PLANNING DESIGN & RES