Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Ultra-shallow earth-covered subway shield traversing operation tunnel construction method of

A technology of tunnel construction and shallow overburden, which is used in tunnels, tunnel linings, and earth-moving drilling and mining to prevent floating and deformation.

Active Publication Date: 2012-11-28
SHANGHAI TUNNEL ENG CO LTD
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In addition, when excavating under ultra-shallow soil conditions, if you need to cross the road, you will also face the risk of crossing large public pipelines and high-pressure pipelines at close range

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Ultra-shallow earth-covered subway shield traversing operation tunnel construction method of
  • Ultra-shallow earth-covered subway shield traversing operation tunnel construction method of
  • Ultra-shallow earth-covered subway shield traversing operation tunnel construction method of

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0011] Further details will be given below in conjunction with specific engineering examples on which the present invention is based.

[0012] The engineering embodiment that the present invention relies on is the interval project between Xujiahui Station and Zhaojiabang Road Station in the second phase 6 section of a certain line of Shanghai Rail Transit. During the excavation of the shield, it is necessary to pass through Xujiahui Park, Hengshan Road and Tianping Road, and the tunnels between Xujiahui Station and Hengshan Road Station of Metro Line 1 under the condition of ultra-shallow covering soil. The depth of overburden in the ultra-shallow overburden excavation section is 4.2-5.0m. When passing through the tunnel of Metro Line 1, the minimum clear distance between the shield machine and the tunnel of Line 1 is 0.83m; when passing through the Hengshan Road Φ900 rainwater pipe, the clear distance is 0.34m. It is extremely rare to pass through the operating subway tunnel...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to an ultra-shallow earth-covered subway shield traversing operation tunnel construction method, comprising the following steps of: a. preparation before construction: (1) identifying the work condition within a traversing range before constructing; (2) modifying subway shield equipment; (3) modifying a duct piece; and (4) carrying out protection treatment on underground pipelines within the traversing range; b. actual construction: (1) dividing the ultra-shallow earth-covered subway shield traversing range into a test segment, a traversing segment and a control segment after the traversing, acquiring the optimized parameter configuration of subway shield tunnelling construction when the subway shield traversing tunnel is tunnelled on the test segment, and guiding the subway shield traversing segment tunnelling construction; (2) implementing anti-floating measures within the traversing range; (3) after the traversing, carrying out secondary tracking grouting on the upper part of a traversed tunnel in the constructed tunnel to further stabilize the soil bodies and prevent the subsequent deformation; and (4) keeping to monitor the deformation conditions of the ground and the settlement conditions of the traversed tunnel in the construction process, and summarizing monitoring data to a computer of a command center.

Description

technical field [0001] The invention relates to a shield tunneling construction method, in particular to a shield tunneling construction method for a shield tunnel to safely pass through an operating subway tunnel under the condition of ultra-shallow soil covering. Background technique [0002] With the rapid development of urban rail transit construction, the number of subway construction and operation lines is gradually increasing. The subways in urban areas are all underground lines, and most of them are constructed by shield tunneling method. Due to the needs of rail transit network, subway lines need to criss-cross to form a rail transit network extending in all directions. Therefore, in the process of rail transit construction, more and more shield tunneling operations or subway tunnels under construction are encountered. Considering the cost, construction technology and risks in the planning and design of subway lines, in order to facilitate construction and control ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/04E21D9/093E21D11/04
Inventor 李刚吴惠明顾春华陶育吴列成金国鑫邓喜
Owner SHANGHAI TUNNEL ENG CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products