Embodiment 1
[0027] As shown in the figure, a negative pressure construction method for the tower foundation used in the river, the steps are as follows:
[0028] 1. Drainage: build a dam 6m upstream of the pre-construction site 1 to intercept the river water, and conduct drainage to discharge the river water downstream by bypassing the pre-construction site.
[0029] 2. Excavation of the foundation pit: adopt the large excavation form of natural grading, and use the water pump 3 to discharge the river water infiltrated into the foundation pit 2 to the downstream of the foundation pit 2 during the excavation process; Excavate the slope until the specified depth is dug.
[0030] Under the condition that quicksand is serious and the influence of quicksand cannot be eliminated by enlarging the excavation slope, the construction method of loosening wooden piles 7 around the foundation pit 2 and placing earth retaining boards 8 to block quicksand is adopted.
[0031] Pine piles 7 are drilled a...
Embodiment 2
[0039] As shown in the figure, a negative pressure construction method for the tower foundation used in the river, the steps are as follows:
[0040] 1. Drainage: build a dam 8m upstream of the pre-construction site 1 to intercept the river water, and conduct drainage to discharge the river water downstream by bypassing the pre-construction site.
[0041] 2. Excavation of the foundation pit: adopt the large excavation form of natural grading, and use the water pump 3 to discharge the river water infiltrated into the foundation pit 2 to the downstream of the foundation pit 2 during the excavation process; Excavate the slope until the specified depth is dug.
[0042] Under the condition that quicksand is serious and the influence of quicksand cannot be eliminated by enlarging the excavation slope, the construction method of loosening wooden piles 7 around the foundation pit 2 and placing earth retaining boards 8 to block quicksand is adopted.
[0043] Pine piles 7 are driven at...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com