The invention discloses a reinforcement construction method of a water-rich
quicksand stratum deep-buried pipeline inspection well
system, which comprises the steps of S1, planning and positioning, S2, inspection well sectional type pouring, S3, connecting end head installation, S4, bottom plate foot-lock anchor rod installation, S5, bottom plate reinforcement anchor rod installation, S6, grouting drainage
pipe installation, S7, bottom plate pouring, S8, crossing section pipeline installation, S9, jet grouting
pile construction, S10, grouting drainage construction and the like. And therefore, the whole deep-buried pipeline inspection well reinforcement construction process of the water-rich
quicksand stratum is completed. According to the reinforcement construction method for the water-rich
quicksand stratum deep-buried pipeline inspection well
system, operation is easy, construction is convenient, the
shear strength of a deep-buried
sewage pipeline and the
sedimentation or floating resistance of an inspection well can be effectively improved, the damage risk of the deep-buried
sewage pipeline is reduced, and safety and reliability are achieved.