A Construction Organization Method with Multiple Steps and Multiple Pilot Tunnels
What is Al technical title?
Al technical title is built by PatSnap Al team. It summarizes the technical point description of the patent document.
A multi-step, multi-step technology, which is applied in earthwork drilling, shaft equipment, shaft lining, etc., can solve the problems of limited construction site, many crossing operations of pilot tunnels, complex construction of multiple steps and multiple pilot tunnels, etc., and achieve balanced soil, The effect of reducing construction interference and facilitating material transportation
Active Publication Date: 2021-03-09
CHINA RAILWAY 18TH BUREAU GRP CO LTD +1
View PDF3 Cites 0 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
Large-section shallow-buried underground excavation tunnels usually use temporary supports to divide the section into multi-step and multi-pilot tunnels for underground excavation construction. The construction of multi-step and multi-pilot tunnels is complicated, the construction site is limited, and there are many cross-cutting operations between the pilot tunnels, and many construction organization problems are faced. , there is an urgent need for a scientific construction organization method
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment Construction
[0026] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
[0027] The purpose of the present invention is to provide a multi-step and multi-pilot construction organization method, which follows the eighteen-character guideline of "leading pipes, strict grouting, short excavation, strong support, fast closure, and frequent measurement", which is scientific, reasonable and safe. Reliable, the construction of each step and each guide tunnel is coordinated and orderly, reducing construction interference, rationally allocat...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
PUM
Login to view more
Abstract
The invention discloses a multi-step and multi-pilot construction organization method, comprising the following steps: step 1: adopting pipe curtain combined with freezing construction technology and grouting method to carry out advance support; step 2, excavating the first-step pilot tunnel Step 3, carry out the excavation of the second step pilot tunnel; Step 4, carry out the excavation of the third step pilot tunnel; Step 5, carry out the excavation of the fourth step pilot tunnel; Step 6, carry out the excavation of the fifth step pilot tunnel Excavation. The multi-step and multi-pilot construction organization method provided by the present invention follows the eighteen-character guideline of "leading pipes, strict grouting, short excavation, strong support, fast closure, and frequent measurement", which is scientific, reasonable, safe and reliable, and follows the " The 18-character policy of pipe ahead, strict grouting, short excavation, strong support, fast closure, and frequent measurement is scientific, reasonable, safe and reliable, and the construction of each step and each pilot tunnel is advanced in a coordinated and orderly manner, reducing construction interference and reasonable Allocation of resources improves the efficiency of construction organization.
Description
technical field [0001] The invention relates to the technical field of tunnel construction, in particular to a multi-step and multi-pilot construction organization method. Background technique [0002] In my country, after long-term theoretical guidance and practical exploration, the construction methods of tunnels have become more diversified, and the construction technology has become more mature, such as traditional mine method, new Austrian method, tunnel open (cover) excavation method, shallow buried underground excavation method and shield method etc. Corresponding to different geological conditions and construction techniques, taking comprehensive consideration of construction safety, construction cost and construction speed, etc., the construction of tunnel projects also adopts scientific and reasonable construction organization methods suitable for the geological conditions and construction techniques of the project. , in order to meet the construction requirements ...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.