Construction method for shallow foundation reinforcement

A construction method and shallow foundation technology, applied in infrastructure engineering, foundation structure repair, construction, etc., can solve problems such as waste of cost, complexity, and delay in construction period, and achieve the effects of convenient construction, high safety, and low construction cost

Active Publication Date: 2021-04-09
马鞍山钢铁建设集团有限公司
View PDF7 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] Aiming at the disadvantages of using the order of "shallow first and then deep" in the prior art to reinforce and support the built shallow foundation buildings, the operation is relatively complicated, the construction period is delayed, and the cost is wasted. The Construction Method of Shallow Foundation Reinforcement

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for shallow foundation reinforcement
  • Construction method for shallow foundation reinforcement

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0043] Such as figure 1 , figure 2 As shown, a construction method for shallow foundation reinforcement of the present invention specifically includes the following steps:

[0044] Step 1: Construction preparation, determine construction related parameters

[0045] (1) Before the excavation of the built shallow foundation 3 (a number of fixed piles 4 are installed under the shallow foundation 3 for support), measure and position the line on the natural floor according to the uppermost edge of the earthwork excavation, and spread out the foundation earthwork with lime Dig the upper edge.

[0046] (2) Determine the bottom elevation of the built shallow foundation for mechanical earthwork excavation. Since there is a deep foundation floor around the built shallow foundation 3, the excavation is carried out on the basis of the deep foundation floor around the built shallow foundation 3 to the shallow foundation At the bottom elevation, carry out vertical section steel hoop 2 p...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method for shallow foundation reinforcement, and belongs to the technical field of building construction. The construction method specifically includes the following steps that (1) construction preparation is conducted, and construction related parameters are determined; (2) earth around a shallow foundation is excavated to a designed elevation; (3) layered construction of section steel hoops is conducted; (4) deep foundation earthwork layered excavation is constructed; (5) concrete support layered is conducted; and (6) deep foundation structure construction is conducted and deep and shallow foundation earthwork backfill construction is conducted. By the adoption of the technical scheme, the problems that when construction is conducted according to the sequence from shallow to deep in the prior art, the operation of reinforcing and supporting a built shallow foundation building is complex, the construction period is delayed, and the cost is wasted can be effectively solved. Meanwhile, the construction method for shallow foundation reinforcement is simple, high in safety and relatively low in construction cost.

Description

technical field [0001] The invention belongs to the technical field of building construction, and more specifically relates to a construction method for shallow foundation reinforcement. Background technique [0002] In the process of building construction, the traditional foundation construction sequence is usually "deep first, then shallow", which can effectively ensure the safety and stability of the foundation pit and surrounding structures. However, in actual construction, especially in the metallurgical construction process, due to various reasons such as the limited plane space of the construction site and construction organization arrangements, many construction processes adopt the construction sequence of "shallow first and then deep". If the shallow foundation is not strengthened and protected in the early stage, subsequent forced large-scale excavation will most likely cause displacement of the shallow foundation and its superstructure, resulting in greater econom...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D37/00E02D27/48
CPCE02D37/00E02D27/48
Inventor 袁杨钱勇张晓栋
Owner 马鞍山钢铁建设集团有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products