Construction method of pre-building supported and settled foundation on ground and fixing after pre-pressing for high-rise building with basement
A technology for high-rise buildings and construction methods, applied in construction, infrastructure engineering, etc., can solve the problems of investment benefits not being realized as soon as possible, long construction period, inconvenient construction, etc., to avoid safety risks and the impact on the surrounding environment and reduce construction. Cost, waste reduction effect
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2013-12-25
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention belongs to a brand-new construction method of high-rise buildings with multiple basements in the field of construction. It has changed the traditional process of foundation pit support, earthwork excavation, and then structural construction. It proposes that the structure including the basement be prefabricated on the ground, and the support piles extending to the ground are set as the support of the building. The lifting force transmission device gradually moves down the building to the predetermined elevation, during which the upper structure, electromechanical, decoration and other processes can be simultaneously carried out without interruption and continuous construction. A new construction method. Background technique
[0002] ①At present, in the construction of high-rise buildings with many basements, before the excavation of the basement earthwork, it is necessary to set up the corresponding temporary foundation pit support struct...
Examples
Embodiment Construction
[0027] The invention is a brand-new construction method applicable to multi-high-rise buildings with basements. The specific implementation steps are as follows:
[0028] 1. Early stage of construction: construct a flexible cuttable water-stop curtain 3 wider than the thickness of the wall along the perimeter of the basement exterior wall 1, construct concrete supporting piles 6 including steel lattice columns 7 according to the design position and elevation, and install detachable Install steel corbel 8-a and liftable force transmission device 9-a, adjust the top surface of liftable force transmission device 9-a to uniform elevation, level off the construction site, and facilitate ground pre-construction construction.
[0029] 2. Ground pre-construction: Construction of basement exterior wall edge 2 and grid support 4. After reaching strength and demoulding, grid support 4 is directly supported on the top surface of liftable force transmission device 9-a, and construction of ...