Static sounding construction technology for pavement of urban road

A technology of static penetration and construction technology, which is applied in basic structure engineering, construction, on-site foundation soil survey, etc. It can solve problems such as difficulty in anchoring, damage to large-area road surfaces, casualties, etc., and achieves small damage to the road surface, Effect of reducing social impact and construction noise

Active Publication Date: 2016-06-29
SHANXI PROVINCIAL RES INST OF COMM +1
View PDF5 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

During static exploration construction of urban road surface, due to the hard road surface and water stability layer, this method is no longer applicable. If the anchor is forcibly rotated into the road surface, it will not only damage a large area of ​​road surface, but also cannot provide counter force.
Another kind of anchoring device needs to manually support the head of the lower anchor rod. When encountering hard objects during operation, it is difficult to anchor and produce a reaction force, which can easily cause casualties.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Static sounding construction technology for pavement of urban road
  • Static sounding construction technology for pavement of urban road

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0020] A construction technique of static penetrating sounding of urban road pavement, the concrete steps comprising:

[0021] 1) Positioning and setting out: firstly, collect and analyze the data of underground pipelines, and fully understand the distribution of underground pipelines. The influence of the surface buildings (structures) can be shifted after the approval of the design and supervision, and the maximum distance of shifting is 2m. For the shifted drilling position, the work of signing the shift record shall be done well.

[0022] 2) Drilling: Use a Φ73mm drilling water drill at the position where the wire has been laid out to drill holes in the pavement surface and water stabilization layer, and drill the drill until the undisturbed soil under the road surface is exposed. During the drilling process of water drilling, it should be ensured that the drill bit is vertically downward, and protective measures should be taken after the drilling is completed.

[0023] ...

Embodiment 2

[0028] A construction technique of static penetrating sounding of urban road pavement, the concrete steps comprising:

[0029] 1) Positioning and setting out: firstly, collect and analyze the data of underground pipelines to fully understand the distribution of underground pipelines, and then use a total station to carry out on-site measurement and setting out according to the coordinates of the designed drilling holes. The actual position error of the drilling holes is 0.4m; due to the underground pipelines, The influence of the surface buildings (structures) can be shifted after approval of the design and supervision, and the shift distance is 1.5m. For the shifted drilling position, the work of signing the shift record shall be done well.

[0030] 2) Drilling: Use a Φ73mm drilling water drill at the position where the wire has been laid out to drill holes in the pavement surface and water stabilization layer, and drill the drill until the undisturbed soil under the road sur...

Embodiment 3

[0036] A construction technique of static penetrating sounding of urban road pavement, the concrete steps comprising:

[0037] 1) Positioning and setting out: firstly, collect and analyze the data of underground pipelines to fully understand the distribution of underground pipelines, and then use a total station to carry out on-site measurement and setting out according to the coordinates of the designed drilling holes. The actual position error of the drilling holes is 0.4m; due to the underground pipelines, The influence of the surface buildings (structures) can be shifted after approval of the design and supervision, and the shift distance is 1.5m. For the shifted drilling position, the work of signing the shift record shall be done well.

[0038] 2) Drilling: Use a Φ73mm drilling water drill at the position where the wire has been laid out to drill holes in the pavement surface and water stabilization layer, and drill the drill until the undisturbed soil under the road sur...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention belongs to the technical field of road exploitation and particularly relates to a static sounding construction technology for the pavement of an urban road. The static sounding construction technology for the pavement of the urban road specifically includes the steps of paying off in a positioned mode, tapping, installation of a counter-force device, leveling, static sounding and treatment after construction, wherein in the process of installation of the counter-force device, the corresponding ground position of the counter-force device is drilled with a hole through an electric drill, the hole diameter is matched with the diameter of an expansion bolt, the depth of the hole needs to be 5-10 cm larger than the length of the expansion bolt, and the counter-force device is mounted after drilling. Compared with the prior art, the static sounding construction technology for the pavement of the urban road can complete the static sounding construction operation of the pavement of the urban road quickly on the premise of not affecting normal traffic, primary data are provided for design of a next procedure, input of manpower and material resources is greatly lowered, and social influence is reduced. Therefore, the static sounding construction technology for the pavement of the urban road has the following characteristics that the range of damage to the pavement is small, the pavement is likely to recover, construction noise is low, and environmental protection and cleanliness are achieved.

Description

technical field [0001] The invention belongs to the technical field of road survey, and in particular relates to a construction technique of static penetrating sounding of urban road pavement. Background technique [0002] Static exploration is an important part of engineering survey. The existing static exploration technology is mainly aimed at the area where the surface is the soil layer, and there are few discussions on the static exploration technology for urban road pavement. One of the technical difficulties of the static exploration process is to provide sufficient reaction force. At present, most reaction force devices use hydraulic transmission devices to screw the screw rod with ground anchor into the soil to provide reaction force. During static exploration construction of urban road surface, due to the hard road surface and water stability layer, this method is no longer applicable. If the anchor is forcibly rotated into the road surface, it will not only damage ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D1/00
CPCE02D1/00E02D1/022
Inventor 魏义强武军郝卫国隋来才师永翔高辉杨振江吴天军
Owner SHANXI PROVINCIAL RES INST OF COMM
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products