Method for installing switch cabinet during sewage treatment
An installation method and technology for sewage treatment, applied in switchgear, electrical components and other directions, can solve the problems of shortened installation time, inadequate installation, and high efficiency in sewage treatment, and achieve the effect of shortening installation time and high efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0013] A method for installing a switchgear in sewage treatment, comprising the following steps:
[0014] (1) The hoisting port is selected at the gate of the power distribution room, and the height of the door cabinet should be such that the total height of the switch cabinet with the base wooden boat and the rolling carrier can pass through smoothly. If the requirements cannot be met, a hole should be reserved when building the wall hole;
[0015] (2) The switchgear is transported in place, using a combination of truck cranes, rollers, and chain hoists for hauling. A wooden pile is built at the entrance of the power distribution room in advance, and several rollers are placed on the pile, and the outside of the switchgear is removed. Packing, keep the wooden boat at the bottom of the switch, use the crane to lift the 4 special hoisting rings on the top of the switch cabinet, hoist it to the pre-placed roller, use the hoist and manpower to haul it to the side of the foundatio...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com