An Invasive Weed Algorithm for Solving Resource Constrained Project Scheduling
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- GUANGZHOU METRO DESIGN & RES INST
- Publication Date
- 2022-03-08
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the technical field of construction project scheduling. Background technique
[0002] In the design and construction process of construction projects, many units such as the owner unit, general contractor unit, design unit, construction unit, operation and maintenance unit are often involved, and dozens of departments such as architecture, structure, ventilation, water supply and drainage, safety control, and geology are involved. Coordination of professional project design and implementation. These units and specialties will generate a huge amount of information in the construction drawing design, construction construction and building operation and maintenance. This information can be obtained through the BIM system. However, due to the different professional The resources involved are limited, and the dynamically changing information brings new challenges to the allocation and scheduling of resources in each subproject and i...