A regional power grid maintenance plan intelligent identification and auxiliary preparation method
A technology for maintenance planning and regional power grids, which is applied in the directions of calculation, data processing application, forecasting, etc., which can solve the problems of unable to provide analysis of state-based maintenance and maintenance plans, achieve broad application prospects and practicability, significant benefits, and improve rationality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0046] A method for intelligent identification and auxiliary preparation of a regional power grid maintenance plan, comprising the following steps:
[0047] S1: Build an intelligent identification and auxiliary compilation system for regional power grid maintenance plans;
[0048] S2: Through the standard data resources in the power grid cyber-physical fusion system, build a standardized basic database, use fuzzy logic, and according to various constraints affecting intelligent reasoning, including mutually exclusive maintenance, simultaneous maintenance, sequential maintenance, unchangeable maintenance, The maintenance start time and maintenance duration form the maintenance knowledge base;
[0049] S3: Load grid equipment ledger information, maintenance knowledge base information, grid operation data and network parameter information into the regional grid maintenance plan intelligent identification and auxiliary compilation system;
[0050] S4: Read the grid maintenance pl...
Embodiment 2
[0057] The difference between the method for intelligent identification and auxiliary preparation of a regional power grid maintenance plan according to the embodiment of the present invention is different from that of the first embodiment: in S5, for the processing method of the maintenance time, the relevant formula is as follows:
[0058] Mutually exclusive overhaul constraints:
[0059] Simultaneous overhaul constraints:
[0060] Sequential inspection constraints:
[0061] Unchangeable maintenance constraints:
[0062] Maintenance start time constraints:
[0063] Maintenance Continuity:
[0064]
[0065] In the formula: x i and x j are the start maintenance time of the i-th and j-th equipment respectively; The number of days that the maintenance of the i-th equipment lasts; Indicates the unchangeable start time for maintenance of the i-th equipment; X i is the set of allowable maintenance time for the i-th equipment; T is the total number of maintena...
Embodiment 3
[0068] The difference between the method for intelligent identification and auxiliary preparation of a regional power grid maintenance plan according to the embodiment of the present invention and the first and second embodiments is that: in S7, the particle swarm algorithm includes the following steps:
[0069] (1) Initialize the particle swarm and set the relevant parameters of the particle swarm algorithm;
[0070] (2) Calculate the new velocity and position of the particle according to the velocity and position change formula;
[0071](3) Judge whether the termination condition is met, if so, stop the search and output the optimal solution, if not, go to (1).
[0072] Further, in S7, the intelligent diagnosis analysis and adjustment method for the maintenance data includes the following steps:
[0073] (a) Obtain the maintenance network model structure R and the maintenance knowledge base set N from the power grid cyber-physical fusion system, define the traversal node qu...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com