BIM-based building monitoring method and system, equipment and a storage medium
A monitoring system and building technology, applied in the field of equipment, BIM-based building monitoring methods and systems, and storage media, can solve the problems of project overdue, incomplete analysis of project overdue, and inability to know the reasons for overdue in time.
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2021-09-14
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The present application relates to the field of building construction, and in particular to a BIM-based building monitoring method, system, equipment, and storage medium. Background technique
[0002] BIM (Building Information Modeling, or Building Information Modeling) is another important computer application technology that appears in the engineering construction industry after CAD (Computer Aided Design) technology. It has five characteristics of visualization, coordination, simulation, optimization and drawing.
[0003] BIM is a brand-new architectural design, construction, and management method. Based on three-dimensional digital information technology, all the data of planning, design, construction, operation and other stages are included in the 3D model, allowing the entire life cycle of the building When using the model, workers at any stage in the process can make effective and correct decisions based on accurate and complete data.
[0004] ...
Examples
Embodiment Construction
[0048] The following is attached Figure 1-2 The application is described in further detail.
[0049] This application is based on the fact that construction projects tend to be overdue. This proposal is mainly to analyze the cause of overdue. Specifically, this application discloses a BIM-based building monitoring method. Refer to figure 1 , which is a flow chart of the steps of the method, including the steps:
[0050] S1. Regularly obtain construction process information;
[0051] S2. Determine whether the construction process is overdue;
[0052] S3. When the process is overdue, obtain construction personnel information and construction material information;
[0053] S4. Based on the construction personnel information and construction materials information, generate and save overdue records.
[0054]In the embodiment of the present application, in the actual implementation, a construction project must have a very long construction period, and the analysis of the constr...