Construction method for underground continuous wall with conjoined reinforcing cage by topdown construction method
An underground diaphragm wall and steel cage technology, which is applied in excavation, artificial islands, water conservancy projects, etc., can solve the problems of long construction period, concrete bulge, unevenness, etc., and achieve the effect of reducing construction cost and improving project progress.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0042] Example: see Figure 2A to Figure 4 , the underground diaphragm wall of the present invention adopts the reverse construction method, and the formed underground diaphragm wall has a conjoined reinforcement cage, and its construction process is carried out as follows:
[0043] ①. Delineate the width area of the underground diaphragm wall to be built on the ground, Figure 4 The width area of the diaphragm wall is indicated, and the area surrounded by the diaphragm wall is where the building to be built is located. After the diaphragm wall is formed, a deep foundation pit needs to be dug in this area;
[0044] ②, image 3 As shown, prepare the prefabricated pile 1, the two sides of the upper half or the upper 2 / 3 section of the pile body (depending on the depth ratio of the depth of the foundation pit and the bearing layer) are provided with pre-embedded ribs 11 protruding from the pile body, and the The pre-embedded reinforcement is bent and attached to the two sid...