Method for constructing bridge deepwater foundation steel pile casing

A deep-water foundation and construction method technology, which is applied in basic structure engineering, construction, sheet pile walls, etc., can solve the problem of difficult control of the cumulative error of the straightness of the steel casing, the inability of large lifting equipment to enter the site, and the low safety and quality assurance factor. problems, to achieve the effect of strong ability to adapt to changes in hydrological conditions, strong ability to resist construction risks, and economical and reasonable construction investment

Inactive Publication Date: 2011-02-09
CCCC FIRST HIGHWAY XIAMEN ENG
View PDF3 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] 1. The construction period is long. There are 8 steel casings with a single length of 40 meters. The steel casings need to be extended at the pile position and sink to a certain depth below the river bed. The workload of splicing on the water is heavy, and the foundation construction needs at least a dry season;
[0004] 2. The cost is high, and large-scale hoisting equipment is needed to extend the position of the pile on the water. When the construction site is a closed inner lake, the large-scale hoisting equipment cannot enter the site, and the construction risk is high;
[0005] 3. The safety and quality guarantee coefficient is low, and the steel casings are connected to the floating platform for a long time. When 8 steel casings are processed at the same time, the load on the platform is about 180t. The steel casing is lengthened by joints at the pile position, and the cumulative error of the straightness of the steel casing is difficult to control

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for constructing bridge deepwater foundation steel pile casing
  • Method for constructing bridge deepwater foundation steel pile casing
  • Method for constructing bridge deepwater foundation steel pile casing

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0032] see Figure 1 to Figure 5 , the specific construction process is as follows: the steel casing is manufactured in vertical sections, and the length of each section is 2m; the steel casing is welded between the sections on the assembly pedestal, and the two ends are sealed after the connection length is 40m, and one end is set The air inlet is set at the other end, and the water inlet is set at the other end; enter the water by sliding down the slideway, and use a tugboat to float and tow to the bridge position; open the air outlet at the top of the steel casing and the water inlet valve at the bottom of the casing or Switch; the bottom mouth of the steel casing slowly sinks into the water, and the top mouth gradually lifts out of the water until the steel casing is in a vertical suspension state; continue to exhaust to gradually reduce the water outlet height of the steel casing until the steel casing can freely pass through the bottom layer of the floating platform Dist...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Lengthaaaaaaaaaa
Login to View More

Abstract

The invention discloses a method for constructing a bridge deepwater foundation steel pile casing, which relates to a construction scheme of a floating transportation and boat type floating platform positioning system and an air pressure raising and reducing method of the bridge deepwater foundation steel pile casing. The method comprises the following two steps of: after transporting the steel pile casing to a pier position by floating, performing precise planar positioning on the steel pile casing by an adjusted boat type floating platform positioning system; and inflating the steel pile casing by an air compressor to jack the steel pile casing. In the method, a formed steel pile casing is transported in position by floating, the steel pile casing is submerged by the air pressure raising and reducing method, and the self-weight of the steel pile casing and an anchorage system of the floating platform ensure that the verticality of the steel pile casing and a central plane position of the steel pile casing and a pile foundation can meet the precision required by design and construction. The construction method of the invention is suitable for the construction of deepwater pile foundation engineering under the conditions that river beds are inclined uncovered rocks and the like on which fixed drilling platforms cannot root, or lakes, reservoirs (comprising tidal rivers) and the like have the water depth of less than 60 meters and the common wind power of lower than 5 grade.

Description

technical field [0001] The invention relates to a bridge foundation construction method, in particular to a bridge deepwater foundation steel casing floating transportation and a ship-type floating platform positioning system + air pressure lifting method construction method. Background technique [0002] In recent years, according to the national "five vertical and seven horizontal" development plan, my country's expressway construction has entered a period of rapid development. The number of large bridges built in lakes, rivers and offshore areas has gradually increased, and the difficulty of deep-water foundation construction has gradually increased. Steel protection Tube construction is usually assembled and lowered in sections at the pile position. This construction method has the following problems: [0003] 1. The construction period is long. There are 8 steel casings with a single length of 40 meters. The steel casings need to be extended at the pile position and sink...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D5/66
Inventor 王奎王铁法李俊张景春吴生勇宁艳玲黄雄飞
Owner CCCC FIRST HIGHWAY XIAMEN ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products